INSP-Final Inspection | 7/30/2003 | 7/30/2003 | 7/30/2003 | A | PASS |
Rick Jackson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Trent Bice 7/30/2003 11:34:43 AM
|
INSP-Sprinkler Rough-in/Hydro | 7/23/2003 | 7/24/2003 | 7/24/2003 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test is ok 7/24/2003 12:07:56 PM
|
INSP-Supply line flush | 6/4/2003 | 6/4/2003 | 6/4/2003 | P | PASS |
Rick Jackson
|
|
|
|
INSP-Sprinkler Rough-in | 5/19/2003 | 5/19/2003 | 5/19/2003 | P | PART |
Rick Jackson
|
|
|
###-#### UG cover okay; still need flush and hydro 5/19/2003 12:24:26 PM
|
INSP-Sprinkler Rough-in/Hydro | 5/15/2003 | 5/16/2003 | 5/16/2003 | P | PART |
Rick Jackson
|
|
|
Stan will be on site today. Cover inspection and thrust blocks.; Phone #: ###-#### Internet Inspection Request from: Trent Bice UG completed under the road to the apartments; still need to complete the rest of the UG 5/16/2003 4:30:36 PM
|
INSP-Sprinkler Rough-in/Hydro | 5/15/2003 | 5/15/2003 | 5/15/2003 | P | PART |
Rick Jackson
|
|
|
I'll call you when we get half way accross the road.; Phone #: ###-#### Internet Inspection Request from: Trent Bice partial underground; will call when thrust blocks are poured 5/15/2003 3:43:57 PM
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2003 | 3/10/2003 | 3/10/2003 | P | PART |
Rick Jackson
|
|
|
Only 5 foot out, Inspection to cover; Phone #: ###-#### Internet Inspection Request from: Trent Bice 5 foot stub out okay; end of pipe not covered; sleave at floor height okay will recheck when floor is poured 3/10/2003 3:40:58 PM
|
INSP-Sprinkler Rough-in/Hydro | 3/6/2003 | 3/7/2003 | 3/7/2003 | A | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 3/6/2003 at 2:17:24 PM. Contact: ###-####. Inspection cancelled from web by: Trent Bice
|