INSP-Final Inspection | 10/28/2003 | 10/28/2003 | 10/28/2003 | A | PASS |
Troy Cobbley
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 9/3/2003 | 9/4/2003 | 9/4/2003 | A | PART |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover but the EQ bracing still needs to be completed 9/4/2003 12:07:10 PM
|
INSP-Sprinkler Rough-in | 9/2/2003 | 9/3/2003 | 9/3/2003 | A | PART |
Troy Cobbley
|
|
|
The iniatial long section of 3" main need EQ bracing. Electrical and communications contractors to remove wiring from sprinkler pipe hangers. Sprinkler rough-in is OK
9/3/2003 12:13:24 PM 9/3/2003 12:13:53 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/2/2003 | 9/2/2003 | 9/2/2003 | P | PART |
Troy Cobbley
|
|
|
RICK; Phone #: ###-#### Hydro test is OK 9/2/2003 3:46:27 PM
|
INSP-Sprinkler Rough-in/Hydro | 7/21/2003 | 7/22/2003 | 7/22/2003 | A | PASS |
Troy Cobbley
|
|
|
underground supply line hydro is OK 7/22/2003 10:46:16 AM
|
INSP-Supply line flush | 7/21/2003 | 7/22/2003 | 7/22/2003 | A | PASS |
Troy Cobbley
|
|
|
Under ground supply line flush is ok 7/22/2003 10:46:41 AM
|
INSP-Sprinkler Rough-in | 7/16/2003 | 7/17/2003 | 7/17/2003 | A | PART |
Troy Cobbley
|
|
|
jan ###-#### inspection was for coverage of sprinkler piping above the hard lid areas. Sprinkler piping is OK to cover in these areas as marked on the city approved sprinkler plans. 7/17/2003 11:00:11 AM
|
INSP-Conference | 3/17/2003 | 3/21/2003 | 3/21/2003 | A | PASS |
Troy Cobbley
|
|
|
the underground supply piping is ok to cover 3/21/2003 12:18:05 PM
|
INSP-Conference | 3/17/2003 | 3/18/2003 | 3/18/2003 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 3/17/2003 at 1:59:35 PM. Contact: ###-####. stub out for UG okay; sand on top of pipe 3/18/2003 9:48:56 AM
|