INSP-Final Inspection | 1/21/2004 | 1/21/2004 | 1/21/2004 | A | PASS |
Troy Cobbley
|
|
|
|
INSP-Final Inspection | 1/12/2004 | 1/13/2004 | 1/13/2004 | A | FAIL |
Troy Cobbley
|
|
|
Project not ready for final inspection yet. Inspection was for covering the sprinklers in the remodeled existing area. Sprinklers are OK to cover 1/13/2004 9:33:07 AM
|
INSP-Final Inspection | 12/22/2003 | 12/23/2003 | 12/23/2003 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave millers permission for use of the new church pending the completion of the existing church areas 12/23/2003 8:39:13 AM
|
INSP-Sprinkler Rough-in/Hydro | 12/19/2003 | 12/22/2003 | 12/22/2003 | A | PASS |
Troy Cobbley
|
|
|
Overhead sprinkler system hydro test is ok 12/22/2003 12:39:00 PM
|
INSP-Conference | 12/19/2003 | 12/19/2003 | 12/19/2003 | P | DONE |
Troy Cobbley
|
|
|
Spoke with sprinkler contractor about a temporary occupancy 12/19/2003 1:37:19 PM
|
INSP-Sprinkler Rough-in | 12/10/2003 | 12/10/2003 | 12/10/2003 | P | PART |
Troy Cobbley
|
|
|
See approved plans for areas with todays date that are ok to cover 12/10/2003 12:47:55 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/17/2003 | 11/17/2003 | 11/17/2003 | P | PART |
Troy Cobbley
|
|
|
the two uprights and two pendants in the connecting area are ok to cover. I notified Gerald with Treasure Valley Fire that it looks like a upright head will be required in the mechanical chase unless they can meet exception 12 of concealed combustible spaces 11/17/2003 2:19:27 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/3/2003 | 11/3/2003 | 11/3/2003 | P | PART |
Troy Cobbley
|
|
|
sprinklers are ok to cover in the round chapel area in the connection between the new church and the existing area 11/3/2003 2:42:22 PM
|
INSP-Sprinkler Rough-in | 9/25/2003 | 9/25/2003 | 9/25/2003 | P | PART |
Troy Cobbley
|
|
|
The prayer sanctuary sprinkler piping is ok to cover 9/25/2003 2:57:07 PM
|
INSP-Sprinkler Rough-in | 9/12/2003 | 9/12/2003 | 9/12/2003 | P | PART |
Troy Cobbley
|
|
|
south half of sanctuary is ok to cover 9/12/2003 2:56:52 PM
|
INSP-Sprinkler Rough-in | 9/9/2003 | 9/9/2003 | 9/9/2003 | P | PART |
Troy Cobbley
|
|
|
###-#### mike The high vaulted ceiling in the sanctuary area, the high ceiling area to the immediate north and the lower soffit area to the north is ok to cover 9/9/2003 2:00:00 PM 9/9/2003 2:01:35 PM
|
INSP-Sprinkler Rough-in | 8/18/2003 | 8/19/2003 | 8/19/2003 | P | PART |
Troy Cobbley
|
|
|
See approved job site plans for areas with deficencies 8/19/2003 4:10:12 PM
|
INSP-Sprinkler Rough-in | 8/18/2003 | 8/18/2003 | 8/18/2003 | P | PART |
Troy Cobbley
|
|
|
MIKE ###-#### I looked at the piping in the high ceiling area that runs east/west and it is ok to cover. The piping as installed in the high ceiling areas that run north/south do not match plans and need to be resubmitted 8/18/2003 4:20:18 PM
|