Permit Information
Permit NumberFIR03-00239
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 11 N LATAH ST
Project NameSPR AHAVATH BETH ISRAEL
Customer Number 
ePlanReview 
Description
(AHAVATH BETH ISRAEL) * Phase I - To install underground fire service main from N. Latah street (property line, west approximately 778'-0" into the west side of an 8,500-ft/2 Ahavath Beth Israel Multi-purpose Building Assembly Hall. Phase II - To install underground fire service main from North side of the Assembly building approximately 95'-0" to the South side of the proposed Library building. All underground, (excluding the risers and supply through the floors) is 6" C-900 PVC fire service main. The fire sprinkler underground work shall comply with NFPA 13-1999, NFPA 24-1995 and the UFC-1997, attached review comment and conditions list, all as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD03-00964.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Sprinkler Rough-in/Hydro3/1/20043/1/20043/1/2004PPASS
DetailsRick Jackson
UG hydro okay 3/1/2004 5:20:56 PM
INSP-Supply line flush1/28/20041/28/20041/28/2004PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 1/28/2004 at 7:45:44 AM. Contact: ###-####. UG flush only - okay 1/28/2004 1:05:16 PM
INSP-Sprinkler Rough-in/Hydro9/8/20039/8/20039/8/2003PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 9/8/2003 at 8:11:17 AM. Contact: ###-####. okay to cover up base of riser and 22 thrust block to west of riser 9/8/2003 12:50:06 PM
INSP-Sprinkler Rough-in/Hydro8/27/20038/27/20038/27/2003PPART
DetailsTroy Cobbley
The underground supply between both buildings is ok to cover 8/28/2003 8:11:49 AM
INSP-Sprinkler Rough-in6/10/20036/10/20036/10/2003APART
DetailsRick Jackson
okay to cover; need to flush and hydro test 6/10/2003 1:21:19 PM
INSP-Conference5/15/20035/16/20035/16/2003PNR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 5/15/2003 at 5:13:41 PM. Contact: ###-####. not ready for thrust blocks 5/16/2003 4:29:48 PM
INSP-Conference5/15/20035/16/20035/16/2003APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 5/15/2003 at 5:14:16 PM. Contact: ###-####.this inspection was completed on 5/15 5/16/2003 10:09:09 AM
INSP-Sprinkler Rough-in5/15/20035/15/20035/15/2003PPART
DetailsRick Jackson
need thrust blocks; not installed to property line;