INSP-Final Inspection | 11/26/2003 | 11/26/2003 | 11/26/2003 | P | PASS |
Troy Cobbley
|
|
|
|
INSP-Final Inspection | 10/10/2003 | 10/10/2003 | 10/10/2003 | P | PART |
Troy Cobbley
|
|
|
NAC panels had to be replaced due to excessive current draw. Manufacture sent out a temp. replacement panel that still draws more power than original design. New panels will be in within 5 days. The panels installed require 7.6 ah batteries to meet code. 7 ah are installed.
|
INSP-Final Inspection | 10/8/2003 | 10/8/2003 | 10/8/2003 | P | FAIL |
Troy Cobbley
|
|
|
update map in clubhouse, alarm signals are not correct and need to be redone, need 14.6 ah batteries in the nac panel 10/8/2003 3:35:57 PM
|
INSP-Final Inspection | 10/7/2003 | 10/7/2003 | 10/7/2003 | P | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/7/2003 at 11:25:04 AM. Contact: ###-####. need to reschedule when other fire/life safety items are ready 10/8/2003 7:39:29 AM
|
INSP-Final Inspection | 10/3/2003 | 10/6/2003 | 10/6/2003 | A | FAIL |
Troy Cobbley
|
|
|
alarm contractor was not able to make inspection 10/6/2003 2:52:38 PM
|
INSP-Final Inspection | 9/30/2003 | 9/30/2003 | 9/30/2003 | P | CANC |
Troy Cobbley
|
|
|
wrong inspection called in 9/30/2003 3:49:55 PM
|