INSP-Final Inspection | 4/22/2004 | 4/22/2004 | 4/22/2004 | P | PASS |
Rick Jackson
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 3/18/2004 | 3/19/2004 | 3/19/2004 | A | PASS |
Rick Jackson
|
|
|
Tom ###-#### okay to cover; additional heads added at lobby due to finished ceiling height; will close this out final inspection to verify escutcheons 3/19/2004 10:15:27 AM
|
INSP-Sprinkler Rough-in/Hydro | 3/4/2004 | 3/5/2004 | 3/5/2004 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 3/4/2004 at 3:08:59 PM. Contact: ###-####. okay to cover lobby area 3/5/2004 3:26:37 PM
|
INSP-Sprinkler Rough-in | 11/25/2003 | 11/26/2003 | 11/26/2003 | A | PART |
Rick Jackson
|
|
|
phase one is okay to cover; see plans for area 11/26/2003 9:21:41 AM
|
INSP-Sprinkler Rough-in/Hydro | 11/25/2003 | 11/25/2003 | 11/25/2003 | P | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/25/2003 at 8:54:25 AM. Contact: ###-####. rescheduled by inspector to 11/26 at 8:00 am 11/25/2003 4:49:13 PM
|
FIR-Aging Inspection | 9/10/2003 | 9/10/2003 | 9/10/2003 | | PASS |
Rick Jackson
|
|
|
wip 9/10/2003 7:59:29 AM
|