INSP-Final Inspection | 6/18/2004 | 6/21/2004 | 6/21/2004 | A | PASS |
Troy Cobbley
|
|
|
All items on the correction notice corrected. 6/21/2004 1:24:20 PM
|
INSP-Final Inspection | 6/18/2004 | 6/18/2004 | 6/18/2004 | P | PASS |
Troy Cobbley
|
|
|
permit finaled 6/18/2004 3:39:43 PM
|
INSP-Final Inspection | 6/16/2004 | 6/17/2004 | 6/17/2004 | A | FAIL |
Troy Cobbley
|
|
|
provide correct canopies on all of the sprinkler pendants in the common areas on all floors. Per review note #3 lintels are to be provided above showers. No lintels have been provided. Sprinkler coverage is blocked by stub wall. Provide hydraulic test certificates. Provide additional heads for spare head cabinet (6 of each type) See note #42. 6/17/2004 3:10:36 PM
|
INSP-Final Inspection | 6/16/2004 | 6/16/2004 | 6/16/2004 | P | FAIL |
Troy Cobbley
|
|
|
Per the sprinkler fitter, he could not get the forward flush to pass. He will need to repipe drains. Room 203 sprinkler canopy is missing. Could not perform complete sprinkler inspection due to fire alarm inspection taking so long. 6/16/2004 3:42:43 PM
|
INSP-Sprinkler Rough-in/Hydro | 6/2/2004 | 6/3/2004 | 6/3/2004 | A | PASS |
Rick Jackson
|
|
|
24 hour air test okay 6/3/2004 11:02:50 AM
|
INSP-Sprinkler Rough-in | 6/1/2004 | 6/2/2004 | 6/2/2004 | A | PART |
Rick Jackson
|
|
|
Contact Brian - 24 Air Test; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Start air test 44 psi 6/2/2004 11:49:07 AM
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2004 | 6/2/2004 | 6/2/2004 | A | PASS |
Rick Jackson
|
|
|
Contact - Brian -- Hydro Test; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Wet system hydro okay 6/2/2004 11:46:44 AM
|
INSP-Sprinkler Rough-in | 4/14/2004 | 4/14/2004 | 4/14/2004 | P | PASS |
Troy Cobbley
|
|
|
second floor corridor sprinkler piping is ok to cover 4/14/2004 4:36:31 PM
|
INSP-Sprinkler Rough-in | 4/8/2004 | 4/9/2004 | 4/9/2004 | A | PASS |
Troy Cobbley
|
|
|
third floor corridor sprinkler piping is ok to cover 4/9/2004 9:30:59 AM
|
INSP-Sprinkler Rough-in | 4/7/2004 | 4/7/2004 | 4/7/2004 | P | CANC |
Troy Cobbley
|
|
|
Contact - Brian -- 3rd Floor Rough In; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2004 | 3/4/2004 | 3/4/2004 | P | PART |
Troy Cobbley
|
|
|
Inspection was a hydro test. The hydro test passed but will need to be done again due to more sprinkler heads being cut into the piping as the project gets closer to completion 3/4/2004 3:44:08 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/16/2004 | 2/17/2004 | 2/17/2004 | A | PART |
Troy Cobbley
|
|
|
Sprinkler piping tie-ins from the second to the third floor are connected and ok for cover 2/17/2004 11:44:43 AM
|
INSP-Sprinkler Rough-in/Hydro | 2/12/2004 | 2/13/2004 | 2/13/2004 | A | PART |
Troy Cobbley
|
|
|
1st and 2nd floor hydro test passed 2/13/2004 4:13:22 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/11/2004 | 2/12/2004 | 2/12/2004 | P | FAIL |
Troy Cobbley
|
|
|
Sprinkler rough-in on the first floor is ok. Insulation inspection is needed before covering can be done.
Sprinkler rough-in on the second floor is ok except for hangers and supports are needed for the plastic piping mains. Also verification is needed that the piping changes to the rise up to the second floor do not adversely affect the hydraulic calculations 2/12/2004 3:24:10 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/3/2004 | 2/4/2004 | 2/4/2004 | A | CANC |
Troy Cobbley
|
|
|
Inspection needed was a cover inspection. See fir03-00554 2/4/2004 8:59:18 AM
|
INSP-Sprinkler Rough-in | 1/30/2004 | 1/30/2004 | 1/30/2004 | P | FAIL |
Troy Cobbley
|
|
|
tenting not completed 1/30/2004 12:27:06 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2004 | 1/29/2004 | 1/29/2004 | P | PART |
Troy Cobbley
|
|
|
dry system hydro test and the underground hydro test are OK. Rough-in for the 3rd floor wet system is OK. Still needs a tenting inspection 1/29/2004 3:50:25 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/27/2004 | 1/28/2004 | 1/28/2004 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 1/27/2004 at 1:32:24 PM. hydro on dry system failed; other items corrected for dry system 1/28/2004 12:18:21 PM
|
INSP-Sprinkler Rough-in | 1/21/2004 | 1/21/2004 | 1/21/2004 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for the rough-in on the attic dry system. Some hangers on the 4" main need to be attached to the top chord of the trusses and two EQ bracings need to be attached to the wall plate. Also need to provide signage showing location of the FDC 1/21/2004 3:03:54 PM
|
INSP-Sprinkler Rough-in/Hydro | 12/1/2003 | 12/2/2003 | 12/2/2003 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/1/2003 at 2:45:36 PM. UG flush only okay 12/2/2003 8:35:11 AM
|
INSP-Sprinkler Rough-in/Hydro | 11/13/2003 | 11/14/2003 | 11/14/2003 | A | DONE |
Troy Cobbley
|
|
|
Inspection was actually a conference on sprinklers spaced off of obstructions in the nfpa 13 areas 11/14/2003 11:10:20 AM
|
INSP-Conference | 11/4/2003 | 11/5/2003 | 11/5/2003 | A | DONE |
Troy Cobbley
|
|
|
I spoke with the sprinkler fitter about sprinkler spacing from light fixtures. Per NFPA 13R the pendants need to be 3'6" to 4' from the fixtures. 11/5/2003 2:28:35 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/26/2003 | 8/27/2003 | 8/27/2003 | A | PART |
Troy Cobbley
|
|
|
Underground supply line is ok to cover. One section of the piping rises to within 4' of the existing grade but the excavator stated that another 10" of roadmix and then a layer of blacktop would be over it. I contacted Debest Fire and told them that I was giving an ok to cover and that if conduit was needed in the trench for PIV tamper they had better do it now. The control vavle location was not shown on the plans 8/27/2003 10:41:57 AM
|