INSP-Final Inspection | 3/16/2004 | 3/16/2004 | 3/16/2004 | P | PASS |
Troy Cobbley
|
|
|
fire sprinkler system finaled
|
INSP-Final Inspection | 3/9/2004 | 3/11/2004 | 3/11/2004 | A | FAIL |
Troy Cobbley
|
|
|
Fire sprinkler system is ready to final when the alarms have been tested 3/11/2004 9:31:44 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2004 | 2/2/2004 | 2/2/2004 | A | PART |
Troy Cobbley
|
|
|
above ground hydro test is OK 2/2/2004 11:28:28 AM
|
INSP-Sprinkler Rough-in | 1/29/2004 | 1/30/2004 | 1/30/2004 | A | PART |
Troy Cobbley
|
|
|
Both janitor rooms and the 2nd floor Programs room is OK to cover 1/30/2004 7:26:30 AM
|
INSP-Sprinkler Rough-in | 1/30/2004 | 1/30/2004 | 1/30/2004 | P | PART |
Troy Cobbley
|
|
|
hydro test on the fdc is ok. Hydro test on the overhead system failed 1/30/2004 11:52:34 AM
|
INSP-Sprinkler Rough-in | 1/22/2004 | 1/22/2004 | 1/22/2004 | P | PART |
Troy Cobbley
|
|
|
both day rooms, laundry room and sewing room are ok to cover the sprinkler piping 1/22/2004 1:15:16 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/6/2004 | 1/7/2004 | 1/7/2004 | A | PART |
Troy Cobbley
|
|
|
rick ; Phone #: ###-#### See approved plans for locations that are ok to cover with todays date 1/7/2004 11:23:25 AM
|
INSP-Sprinkler Rough-in | 12/19/2003 | 12/19/2003 | 12/19/2003 | P | PART |
Troy Cobbley
|
|
|
see approved plans for hardlid locations where the sprinkler piping is OK to cover with todays date 12/19/2003 2:35:29 PM
|
INSP-Conference | 12/11/2003 | 12/12/2003 | 12/12/2003 | A | PART |
Rick Jackson
|
|
|
Rick; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes met with Rick of TVFP about the close proximity (less than 6 ft) of the sidewall heads at the doors to the cells; this occurs at the ends of the cell/day room areas; per Bill Alexander a baffle will be needed to separate the sidewall heads; this info was given to Greg Johnson via telephone call 12/12/2003 9:51:14 AM
|
INSP-Sprinkler Rough-in | 10/31/2003 | 11/3/2003 | 11/3/2003 | A | PART |
Troy Cobbley
|
|
|
inspection was for hangers in the fire sprinkler riser room. Hangers are ok to fire proof 11/3/2003 12:20:03 PM
|
INSP-Supply line flush | 10/24/2003 | 10/24/2003 | 10/24/2003 | P | PASS |
Troy Cobbley
|
|
|
underground flush is OK 10/24/2003 3:29:21 PM
|
INSP-Supply line flush | 10/20/2003 | 10/20/2003 | 10/20/2003 | P | CANC |
Troy Cobbley
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2003 | 10/13/2003 | 10/13/2003 | P | PART |
Rick Jackson
|
|
|
RICK; Phone #: ###-#### Internet Inspection Request from: Annette Moore verified hangers/straps in dayroom area and east side cells; okay to fireproof 10/13/2003 9:44:15 AM 10/13/2003 10:51:22 AM
|
INSP-Sprinkler Rough-in | 10/1/2003 | 10/1/2003 | 10/1/2003 | P | PART |
Rick Jackson
|
|
|
###-#### checked the new laundry area only; this area will be fire proofed throughout and all hangers have straps at top of joists 10/1/2003 2:21:32 PM
|
INSP-Sprinkler Rough-in | 9/18/2003 | 9/19/2003 | 9/19/2003 | A | PART |
Troy Cobbley
|
|
|
Inspection was for the hangers for the 3" main in the west side of the new building. They are OK. Also inspected was the 2 1/2" main and drop downs on the west side holding cells 9/19/2003 4:14:54 PM
|