INSP-Sprinkler Rough-in/Hydro | 2/20/2004 | 2/20/2004 | 2/20/2004 | P | PASS |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 2/20/2004 at 8:58:08 AM. Contact: ###-####.
|
INSP-Final Inspection | 2/10/2004 | 2/10/2004 | 2/10/2004 | P | FAIL |
Troy Cobbley
|
|
|
forward flow of the backflow preventor failed. Only got 12 psi through the 2" main drain but needed 35 psi
|
INSP-Sprinkler Rough-in/Hydro | 2/5/2004 | 2/6/2004 | 2/6/2004 | P | CANC |
Troy Cobbley
|
|
|
###-####
|
INSP-Sprinkler Rough-in/Hydro | 2/3/2004 | 2/5/2004 | 2/5/2004 | P | PASS |
Troy Cobbley
|
|
|
Items on the correction notice have been corrected and the overhead hydro test is OK 2/5/2004 2:55:43 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/28/2004 | 1/29/2004 | 1/29/2004 | A | FAIL |
Troy Cobbley
|
|
|
above ground hydro test failed 1/29/2004 9:52:47 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/28/2004 | 1/28/2004 | 1/28/2004 | P | FAIL |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie didn't hold pressure - hydro failed 1/28/2004 1:59:32 PM
|
INSP-Sprinkler Rough-in/Hydro | 12/22/2003 | 12/23/2003 | 12/23/2003 | P | PASS |
Troy Cobbley
|
|
|
underground hydro test and the 24 hour air test on the dry pipe system is ok 12/23/2003 3:37:24 PM
|
INSP-Sprinkler Rough-in/Hydro | 12/22/2003 | 12/22/2003 | 12/22/2003 | P | PART |
Troy Cobbley
|
|
|
24 hour test for the dry system started at 2:00 and had 40 psi on the guage
|
INSP-Sprinkler Rough-in/Hydro | 12/22/2003 | 12/22/2003 | 12/22/2003 | P | PART |
Troy Cobbley
|
|
|
Underground supply line flush is OK. For the sprinkler rough-in the upright sprinkler branchlines in the center section are overspaced, provide nipple extender for upright sprinkler head blocked by overhead door hardware on the south side, provide high temp head in front of unit heater, reinstall hanger in the southeast office, provide insulation on bottom chords of trusses in fab area so pendants could operate 12/22/2003 3:27:20 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2003 | 11/6/2003 | 11/6/2003 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 11/6/2003 at 8:40:44 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Nov 6 2003 8:42AM.
|
INSP-Sprinkler Rough-in/Hydro | 11/5/2003 | 11/6/2003 | 11/6/2003 | A | PART |
Troy Cobbley
|
|
|
Underground supply line is ok to cover. The connection to United Waters portion of the pipe has not been made yet. 11/6/2003 3:59:13 PM
|