Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR03-00594
StatusFinaled
Name DE BEST FIRE PROTECTION
Site Address 1649 N AMBER ST
Project NameSPR RM INVESTMENT
Customer Number 
ePlanReview 
Description
(VANILLA FINISH-NO TENANT) To provide underground supply line and overhead dry pipe system in an existing building. To remodel portions of a 3,106 sq.ft. future tenant space. Work includes selective demolition of restroom; construction of new interior walls to create a fully complying accessible restroom and construct a 1-hour fire barrier wall between the two tenant spaces & to construct a 1-hour wall with parapet at the west wall due to proximity to property line; add service sink & relocate water heater per approved plans. Field review and approval by fire inspector required. Note: per letter of agreement on file, this entire building is required to be fully sprinklered with fire suppression system per NFPA 13 by 1/5/04. NO TENANT ALLOWED UNDER THIS PERMIT. A 'Letter of Compliance" is required for this project.
The fire sprinkler system work shall comply with IFC 2000, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD03-01348. This permit is not attached to any other permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Sprinkler Rough-in/Hydro2/20/20042/20/20042/20/2004PPASS
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 2/20/2004 at 8:58:08 AM. Contact: ###-####.
INSP-Final Inspection2/10/20042/10/20042/10/2004PFAIL
DetailsTroy Cobbley
forward flow of the backflow preventor failed. Only got 12 psi through the 2" main drain but needed 35 psi
INSP-Sprinkler Rough-in/Hydro2/5/20042/6/20042/6/2004PCANC
DetailsTroy Cobbley
###-####
INSP-Sprinkler Rough-in/Hydro2/3/20042/5/20042/5/2004PPASS
DetailsTroy Cobbley
Items on the correction notice have been corrected and the overhead hydro test is OK 2/5/2004 2:55:43 PM
INSP-Sprinkler Rough-in/Hydro1/28/20041/29/20041/29/2004AFAIL
DetailsTroy Cobbley
above ground hydro test failed 1/29/2004 9:52:47 AM
INSP-Sprinkler Rough-in/Hydro1/28/20041/28/20041/28/2004PFAIL
DetailsRick Jackson
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie didn't hold pressure - hydro failed 1/28/2004 1:59:32 PM
INSP-Sprinkler Rough-in/Hydro12/22/200312/23/200312/23/2003PPASS
DetailsTroy Cobbley
underground hydro test and the 24 hour air test on the dry pipe system is ok 12/23/2003 3:37:24 PM
INSP-Sprinkler Rough-in/Hydro12/22/200312/22/200312/22/2003PPART
DetailsTroy Cobbley
24 hour test for the dry system started at 2:00 and had 40 psi on the guage
INSP-Sprinkler Rough-in/Hydro12/22/200312/22/200312/22/2003PPART
DetailsTroy Cobbley
Underground supply line flush is OK. For the sprinkler rough-in the upright sprinkler branchlines in the center section are overspaced, provide nipple extender for upright sprinkler head blocked by overhead door hardware on the south side, provide high temp head in front of unit heater, reinstall hanger in the southeast office, provide insulation on bottom chords of trusses in fab area so pendants could operate 12/22/2003 3:27:20 PM
INSP-Sprinkler Rough-in/Hydro11/6/200311/6/200311/6/2003PCANC
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 11/6/2003 at 8:40:44 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Nov 6 2003 8:42AM.
INSP-Sprinkler Rough-in/Hydro11/5/200311/6/200311/6/2003APART
DetailsTroy Cobbley
Underground supply line is ok to cover. The connection to United Waters portion of the pipe has not been made yet. 11/6/2003 3:59:13 PM