INSP-Final Inspection | 7/12/2005 | 7/12/2005 | 7/12/2005 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Separate permits to be required for any future work. Phil Omis notified of this fact and agreed.
|
FIR-Aging Inspection | 7/11/2005 | 7/11/2005 | 7/12/2005 | | CANC |
Troy Cobbley
|
|
|
|
INSP-Conference | 7/28/2004 | 7/28/2004 | 7/28/2004 | P | DONE |
Troy Cobbley
|
|
|
Fire alarm inspection for phases 1 and 2 are complete. The fire alarm contractor to resubmit drawings showing what work has been completed and then resubmit drawings for each additional phase that requires a building permit
|
INSP-Alarm Testing | 7/27/2004 | 7/27/2004 | 7/27/2004 | P | PART |
Troy Cobbley
|
|
|
The fire alarm in the south wing, phase II per the building permit is tested and complete. 7/27/2004 3:57:03 PM
|
INSP-Alarm Testing | 1/21/2004 | 1/21/2004 | 1/21/2004 | A | PART |
Troy Cobbley
|
|
|
The items on he correction notice for the annex (north wing) have been completed. The fire alarm in this area is complete 1/21/2004 8:46:27 AM
|
INSP-Alarm Testing | 1/20/2004 | 1/20/2004 | 1/20/2004 | A | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 1/20/2004 at 7:11:15 AM. Contact: ###-####.
|
INSP-Alarm Testing | 1/14/2004 | 1/14/2004 | 1/14/2004 | P | PART |
Troy Cobbley
|
|
|
The annex fire alarm system was tested. All fire alarm devices operated correctly except for one fire smoke damper in the corridor ceiling and the manual pull station at the nurses station. Also need to verify door locking requirements are met for an I-3 occupancy 1/14/2004 1:45:28 PM
|