INSP-Final Inspection | 6/25/2004 | 6/25/2004 | 6/25/2004 | P | PASS |
Rick Jackson
|
|
|
|
INSP-Final Inspection | 6/24/2004 | 6/24/2004 | 6/24/2004 | P | FAIL |
Troy Cobbley
|
|
|
All items on the correction notice have been corrected. Overhead hydro test is complete. Still need to verify that all canopies are installed and that spacing is ok. Pendant head in admin. office is too far down from ceiling.
|
INSP-Sprinkler Rough-in/Hydro | 5/25/2004 | 5/26/2004 | 5/26/2004 | A | FAIL |
Troy Cobbley
|
|
|
backflow preventor was leaking. Hydro test failed 5/26/2004 11:51:47 AM
|
INSP-Sprinkler Rough-in/Hydro | 5/26/2004 | 5/26/2004 | 5/26/2004 | P | PART |
Troy Cobbley
|
|
|
Hydro test on both wet systems, antifreeze system and the FDC passed. 5/26/2004 4:24:47 PM
|
INSP-Sprinkler Rough-in/Hydro | 5/24/2004 | 5/24/2004 | 5/24/2004 | P | CANC |
Troy Cobbley
|
|
|
Complete system was not ready to hydro test so fire sprinkler contractor cancelled at the job site 5/24/2004 3:40:11 PM
|
INSP-Sprinkler Rough-in/Hydro | 4/14/2004 | 4/14/2004 | 4/14/2004 | P | PART |
Troy Cobbley
|
|
|
All items marked for correction on the city approved plans have been corrected except for the upright head in entry lobby 194 is overspaced and the uprights above the gym and cafateria need verified slope match with deck. Ceiling tile is ok to be installed in gym, cafateria and classrooms. 4/14/2004 1:53:45 PM
|
INSP-Sprinkler Rough-in/Hydro | 4/9/2004 | 4/12/2004 | 4/12/2004 | P | PART |
Troy Cobbley
|
|
|
Inspection was for the wet system below the hardlid. See city approved plans for location where hangers need to be added, earthquake bracing added and sprinklers added. 4/12/2004 3:44:44 PM
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2004 | 4/9/2004 | 4/9/2004 | A | FAIL |
Troy Cobbley
|
|
|
could not get access to areas above ceiling in cafateria areas. 4/9/2004 8:47:25 AM
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2004 | 4/8/2004 | 4/8/2004 | A | FAIL |
Troy Cobbley
|
|
|
The onsite sprinkler fitter did not have the approved plans on site for me to perform the inspection 4/8/2004 8:33:19 AM
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2004 | 4/8/2004 | 4/8/2004 | P | FAIL |
Troy Cobbley
|
|
|
See city approved plans for locations of missing hangers and earthquake bracing. Some piping could not be verified due to hard lids already being installed. I spoke to the general contractor about access to these areas. Not all areas have been inspected due to time restraints. Another inspection has been set up for tomorrow morning. 4/8/2004 3:35:02 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2004 | 1/30/2004 | 1/30/2004 | A | PART |
Troy Cobbley
|
|
|
Upright heads have been added along the draft curtain as requested on the last correction notice 1/30/2004 7:27:28 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2004 | 1/23/2004 | 1/23/2004 | A | PART |
Troy Cobbley
|
|
|
east wing attic system is OK to cover but upright heads need to be added on the west side of the draft stop wall and baffles placed between the new heads and the existing 1/23/2004 10:13:42 AM
|
INSP-Sprinkler Rough-in | 12/11/2003 | 12/11/2003 | 12/11/2003 | P | PART |
Rick Jackson
|
|
|
heads overspaced at shear wall as identified on sheet 4 and 5; okay to start covering other areas 12/11/2003 3:04:56 PM
|
INSP-Sprinkler Rough-in/Hydro | 12/11/2003 | 12/11/2003 | 12/11/2003 | P | PART |
Rick Jackson
|
|
|
They are getting ready to sheet rock the bottom of the scissor trusses in two wings. This would be a visual inspection. Please call 1 hour prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice 12/11/2003 2:49:58 PM
|
INSP-Supply line flush | 11/25/2003 | 11/26/2003 | 11/26/2003 | A | PASS |
Troy Cobbley
|
|
|
supply line flush is OK 11/26/2003 9:57:34 AM
|