Permit NumberFIR03-00794
StatusFinaled
Name IDAHO FIRE PROTECTION
Site Address 3250 N SHAMROCK ST
Project NameSPR Kidz Inc. Day Care
Customer Number 
ePlanReview 
Description
Kidz Inc. Day Care * To install a complete underground supply, dry and wet pipe fire sprinkler system in a new 1,840-ft/2 one story, Type VB, I-4 day care building. Fire sprinklers required for the I-4. The fire sprinkler system work shall comply with IFC 2000, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD03-00794.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/5/20043/8/20043/8/2004PPASS
DetailsTroy Cobbley
fire sprinklers finaled 3/8/2004 4:10:31 PM
INSP-Sprinkler Rough-in/Hydro2/23/20042/24/20042/24/2004APART
DetailsTroy Cobbley
24 hour air test is ok and forward flush of the backflow preventor is ok 2/24/2004 9:09:38 AM
INSP-Sprinkler Rough-in/Hydro2/23/20042/23/20042/23/2004PPART
DetailsTroy Cobbley
Inspection is for the 24 hour air test. Pressure is at 41.5 psi 2/23/2004 4:19:18 PM
INSP-Sprinkler Rough-in/Hydro2/19/20042/19/20042/19/2004APART
DetailsTroy Cobbley
above ground and underground hydro test is OK 2/19/2004 12:52:07 PM
INSP-Supply line flush2/13/20042/17/20042/17/2004APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 2/13/2004 at 3:32:01 PM. Contact: ###-####. UG flush okay 2/17/2004 2:44:38 PM
INSP-Supply line flush2/4/20042/5/20042/5/2004APART
DetailsTroy Cobbley
Underground supply is OK to cover 2/5/2004 11:29:17 AM
INSP-Sprinkler Rough-in/Hydro1/12/20041/13/20041/13/2004PFAIL
DetailsTroy Cobbley
24 hour test for the dry pipe system failed. 1/13/2004 2:42:11 PM
INSP-Sprinkler Rough-in/Hydro1/12/20041/12/20041/12/2004PPART
DetailsTroy Cobbley
The 24 hour air test started at 2:30 with 41 lbs. Overhead dry system is ok to cover. Riser and crawl space needs to be inspected. Contractor will provide sheet rock to separate the canopies from the main floor sprinkler system 1/12/2004 4:08:50 PM