Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR04-00004
StatusFinaled
Name DE BEST FIRE PROTECTION
Site Address 6565 W EMERALD ST
Project NameSPR SELAH MEDICAL CENTER
Customer Number 
ePlanReview 
Description
(SELAH MEDICAL CENTER) To modify fire sprinklers related to the construction of 3 offices and a conference room within an existing 12,213ft/2 medical office building. Sprinkler work involved is relocate 4 existing standard response SSP's and relocate and replace 2 with quick response SSP's. The 2 replace will allow incorporating the ceiling reduction allowance and thus allow extending coverage for the difference. This fire sprinkler work is related to interior nonbearing walls and suspended ceilings. This building is fire sprinklered to allow non-fire-resistance rated corridors. The fire sprinkler system work shall comply with IFC 2000, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD03-01575.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/14/200511/14/200511/14/2005PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection11/3/200511/8/200511/8/2005ACANC
DetailsTroy Cobbley
jim; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa cancel cambry
INSP-Final Inspection11/3/200511/4/200511/4/2005AFAIL
DetailsTroy Cobbley
See review note #2 requiring verification of spacing over 148 sq.ft. This applies to the pendant heads in the two north side conference rooms.
INSP-Final Inspection10/31/200510/31/200510/31/2005PNR
DetailsTroy Cobbley
I left a correction notice with Diane at the front desk that if all permits had not been finaled by 11/11/05 the affected areas of the building would be shutdown. I also spoke to scott, the building owner. See building review comments.
FIR-Aging Inspection7/28/20057/28/20058/1/2005 NR
DetailsTroy Cobbley
Jim Danes is not sure that the work has been done. He will verify.
INSP-Conference5/26/20055/26/20055/26/2005PDONE
DetailsTroy Cobbley
I spoke to Jim with DeBest about job status. He said he would follow up.
FIR-Aging Inspection4/6/20044/6/20044/6/2004 NR
DetailsTroy Cobbley
work in progress 4/6/2004 8:19:09 AM
FIR-Aging Inspection4/6/20044/6/20044/6/2004 NR
DetailsTroy Cobbley
work in progress 4/6/2004 8:19:09 AM
INSP-Conference8/17/20059/6/2005 P 
DetailsTroy Cobbley
Follow up for inspection