Permit Information
Permit NumberFIR04-00024
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 1200 N LIBERTY ST
Project NameSPR HEALTH TECHNOLOGY
Customer Number 
ePlanReview 
Description
(AMERICAN INSTITUTE OF HEALTH TECHNOLOGY) To install complete fire sprinkler protection in an existing 2 story 25,017-ft/2 church, for an adult medical education school. Work includes approximately 100'-0" of C-900 tapped off a fire service tap in N. Liberty, running East to a Post Indicator valve then continuing East with a conversion of Ductile Iron under the footing and up through the floor in an existing Classroom #121. The installation of a 4" wet "electric" riser system, and a 4" Central DV-1 Dry Pipe valve riser system, for the unheated cavities and "Temp" Classrooms 124, 139, 140 and 141. All fire sprinkler system and related work shall comply with IFC 2000, stamped plans with attached review comments and conditions list, as regulated by the Fire Chief. This conditions list, assigned permit and fire "Inspection Card" are required to be on site as a requirement, to provide witness of compliance and verification of minimum Fire Code. This permit is attached to building permit: BLD03-02844.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Sprinkler Rough-in/Hydro4/28/20044/29/20044/29/2004APASS
DetailsTroy Cobbley
fire sprinklers finaled 4/29/2004 8:58:17 AM
INSP-Sprinkler Rough-in/Hydro4/21/20044/22/20044/22/2004AFAIL
DetailsTroy Cobbley
See approved plans for locations requiring attention. 4/22/2004 2:14:00 PM
INSP-Sprinkler Rough-in/Hydro4/20/20044/21/20044/21/2004AFAIL
DetailsTroy Cobbley
Resubmitted plans still do not match pipe sizing or layout of what has been installed. One area includes a remote area. See revised city plans for locations of problems. Upright heads in the attic along the east wall are spaced too far off of the wall since existing insulation does not fill the combustible space along the wall. Add insulation or sprinkler heads. There is a combustible cavity above the attic space that requires protection. Inspection stopped at locaton shown on plans. 4/21/2004 9:46:03 AM
INSP-Sprinkler Rough-in/Hydro4/13/20044/14/20044/14/2004APASS
DetailsTroy Cobbley
Wet system and dry system hydro test passed 4/14/2004 11:19:38 AM
INSP-Sprinkler Rough-in/Hydro4/14/20044/14/20044/14/2004PPART
DetailsTroy Cobbley
Underground hydro test passed 4/14/2004 3:25:31 PM
INSP-Supply line flush4/8/20044/9/20044/9/2004APASS
DetailsTroy Cobbley
Underground supply line flush OK 4/9/2004 9:26:58 AM
INSP-Sprinkler Rough-in4/7/20044/8/20044/8/2004PPART
DetailsTroy Cobbley
second floor sprinkler piping rough-in is ok .Other areas I looked at do not match plans. I spoke to Bill Alexander and he agreed with me that resubmittals are needed prior to a rough-in inspection. I left a message on Tom's phone and spoke to the on site sprinkler fitter about it. 4/8/2004 3:26:04 PM
INSP-Sprinkler Rough-in2/12/20042/12/20042/12/2004PPART
DetailsTroy Cobbley
underground supply piping is ok to cover. 2/12/2004 2:48:19 PM
INSP-Sprinkler Rough-in2/11/20042/11/20042/11/2004PFAIL
DetailsTroy Cobbley
need approved insulation detail on site prior to inspection 2/11/2004 2:45:22 PM