INSP-Final Inspection | 10/13/2010 | 10/13/2010 | 10/14/2010 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
FIR-Aging Inspection | 10/5/2010 | 10/5/2010 | 10/13/2010 | | PASS |
Troy Cobbley
|
|
|
|
INSP-Sprinkler Rough-in | 8/5/2010 | 8/5/2010 | 8/6/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Conference | 5/13/2010 | 5/19/2010 | 5/20/2010 | A | DONE |
Troy Cobbley
|
|
|
Per Jeff this one is on the top of his list of items to address.
|
FIR-Aging Inspection | 5/10/2010 | 5/10/2010 | 5/13/2010 | | NR |
Troy Cobbley
|
|
|
Was contacted via email that jeff will be making a site visit and then get a final inspection called in. A follow up inspection has been set up for next week.
|
FIR-Aging Inspection | 3/10/2010 | 3/10/2010 | 3/10/2010 | | NR |
Troy Cobbley
|
|
|
Permit forwarded to Scott for further action with non-responsive contractor.
|
FIR-Aging Inspection | 10/28/2005 | 10/28/2005 | 10/31/2005 | | NR |
Troy Cobbley
|
|
|
Greg is following up
|
FIR-Aging Inspection | 7/22/2005 | 7/22/2005 | 7/25/2005 | | NR |
Troy Cobbley
|
|
|
I spoke to the general contractor sid; Phone #: ###-####, he stated that more sprinkler work is needed and once that is done the inspection would be called in
|
INSP-Final Inspection | 3/23/2004 | 3/23/2004 | 3/23/2004 | P | FAIL |
Troy Cobbley
|
|
|
General contractor needs to finish installing ceiling tile around the sprinkler pendants 3/23/2004 10:20:17 AM
|
INSP-Sprinkler Rough-in/Hydro | 3/17/2004 | 3/17/2004 | 3/17/2004 | P | PART |
Troy Cobbley
|
|
|
sprinklers in rooms 107 and 108 are ok to cover 3/17/2004 2:28:32 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/17/2004 | 2/17/2004 | 2/17/2004 | P | FAIL |
Troy Cobbley
|
|
|
Resubmitted plans have not been issued yet. Resubmitted plans address 14.5 x 14.5 spacing of the sprinkler pendants 2/17/2004 1:14:05 PM
|