INSP-Sprinkler Rough-in/Hydro | 7/29/2004 | 7/29/2004 | 7/29/2004 | P | PASS |
Rick Jackson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Cliff Miller
|
INSP-Final Inspection | 7/6/2004 | 7/6/2004 | 7/6/2004 | P | NR |
Rick Jackson
|
|
|
CLIFF; Phone #: ###-#### Internet Inspection Request from: Annette Moore Cliff called and he will reschedule 7/6/2004 3:41:22 PM
|
INSP-Final Inspection | 5/18/2004 | 5/19/2004 | 5/19/2004 | A | PART |
Rick Jackson
|
|
|
for the final on the in duct detectors; Phone #: ###-#### Internet Inspection Request from: Cliff Miller new in-duct detector was added for the new smoke/fire damper was installed in the west shaft on the third floor; a letter has been submitted to remove the scope of the 1 hr shaft from the floating feather TI to the java coffee shop TI; awaiting plan review response 5/19/2004 4:53:14 PM
|
INSP-Final Inspection | 4/30/2004 | 4/30/2004 | 4/30/2004 | P | PART |
Rick Jackson
|
|
|
A smoke/fire damper is being added on the third floor access at the one hour shaft which will require an in-duct detector and approved for temp occupancy per Dave Miller 4/30/2004 3:43:55 PM
|
INSP-Final Inspection | 4/26/2004 | 4/28/2004 | 4/28/2004 | P | FAIL |
Rick Jackson
|
|
|
Clifford'; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes need in-duct detector and smoke/fire damper at third/fourth floor penetration 4/28/2004 5:05:45 PM
|