Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR04-00301
StatusFinaled
Name AEI
Site Address 802 W BANNOCK ST
Project Namealm - HOFF BLDG-ELEVATOR SHAFT
Customer Number 
ePlanReview 
Description
To provide the capability of activating the exhaust fan for the elevator shaft upon initiation of any elevator lobby smoke detector. Two additional fire/smoke dampers are being added to the 3rd floor exit corridor on the north end of the building.

The associated building permit (BLD 00-01151) is to perform upgrades to the common areas on the 3rd and 4th floors of an existing office building. Work is to include upgrading the existing core restrooms to be more accessible to the disabled, upgrading the existing "corridors" (4th floor) and "passageways" (3rd floor) to meet the 1994 UCBC and the conditions of a code upgrade agreement signed by the Building Official, installing a handrail on one side of the North stairway from the 3rd floor to the basement, and constructing a new corridor wall with protected openings on the 4th floor all per approved drawings and plan review conditions on file. The location of fire sprinkler heads shall comply with NFPA 13-1996 as regulated by the Fire Department. This permit DOES NOT establish a CERTIFICATE OF OCCUPANCY for any tenant. PC-310-00 **CJW** (HOFF BUILDING - 3RD & 4TH FLOOR CORE UPGRADE) This building is fire sprinklered for area increase, because it is a high-rise, and to meet the provisions of the 1994 UCBC.

The associated building permit (BLD 04-00924) is to vent the existing elevator shaft located within an existing historic high rise building. Work is to include a horizontal 2-hr fire-resistive-rated shaft, a horizontal metal duct, and a blower unit. The blower unit will be supplied with emergency power from the existing emergency generator and will be activated by the fire alarm system and a smoke detector located in the elevator shaft. All work shall comply with the approved drawings and the plan review report on file. **CJW** (HOFF BUILDING - ELEVATOR SHAFT VENTING - 12TH FLOOR) This building is fire sprinklered for area increase, because it is a high-rise, and to meet the provisions of the 1994 UCBC.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Alarm Testing6/30/20047/1/20047/1/2004APASS
DetailsRick Jackson
Rick, We would like to schedule an inspection for 7/1/04 in the morning if at all possible, if the morning won't work, early afternoon if at all possible. Please call me at the office, ###-####, or on my cell ###-####, as soon as you can, so that we can be sure to have our guys there on site. Thanks, Jason; Phone #: ###-#### Internet Inspection Request from: Jason Minnick