INSP-Sprinkler Rough-in/Hydro | 9/21/2004 | 9/22/2004 | 9/22/2004 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 9/21/2004 at 5:13:38 PM. Contact: ###-####.
|
INSP-Sprinkler Rough-in/Hydro | 9/21/2004 | 9/21/2004 | 9/21/2004 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 9/21/2004 at 10:12:29 AM. Contact: ###-####. 2 heads will be eliminated and 2 heads installed on both sides of the column; per Bill Alexander approved 9/21/2004 3:05:37 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/15/2004 | 9/16/2004 | 9/17/2004 | P | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 9/15/2004 at 3:18:05 PM. Contact: ###-####. Still under construction; not ready 9/17/2004 11:38:34 AM
|