INSP-Final Inspection | 5/12/2005 | 5/13/2005 | 5/13/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire sprinkler finaled
|
INSP-Final Inspection | 5/2/2005 | 5/3/2005 | 5/3/2005 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for final yet.
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2005 | 5/3/2005 | 5/3/2005 | A | PASS |
Troy Cobbley
|
|
|
I verified that the past deficiencies have been corrected. Need verification that the underground flush has been done.
|
INSP-Sprinkler Rough-in/Hydro | 5/3/2005 | 5/3/2005 | 5/3/2005 | P | PART |
Troy Cobbley
|
|
|
2nd, 3rd and 4th floor hydro tests passed
|
INSP-Sprinkler Rough-in/Hydro | 4/28/2005 | 4/29/2005 | 4/29/2005 | A | PART |
Troy Cobbley
|
|
|
Inspection was for above ground hydro test. All passed except for the second, third and fourth floors. Third and fourth floors fed from same riser
|
INSP-Conference | 4/15/2005 | 4/18/2005 | 4/18/2005 | A | DONE |
Troy Cobbley
|
|
|
to discuss fire damper access in pool room///calvin ###-#### Told hvac contractor that he could either install one large access panel or three smaller ones at the fire dampers for serviceing them. Per him the ceiling where the access doors are to be ins
|
INSP-Sprinkler Rough-in/Hydro | 3/22/2005 | 3/23/2005 | 3/23/2005 | A | PASS |
Troy Cobbley
|
|
|
Okd to cover new 2 inch feed connection at 3 inch main by 3x2 mech tee. This connection for new pool room addition not shown on original approved plans. 3/23/2005 12:21:47 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/25/2005 | 2/25/2005 | 2/25/2005 | A | PART |
Troy Cobbley
|
|
|
THis is for trash chutes and porte-coche. Please call 1 hour prior to arrival. Before 12:00 would be acceptable.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
Prete-Coche, OK to cover. 4th floor and 2nd floor trach chutes, OK to cover.
Requested walk-thorugh on all corridors:
1. 3rd floor North end line required CPVC hanger 11'-6". (If using ring hanger, w/restraint).
2. 11/4" CPVC line in front of elevator is burned and needs replaced.
3. South half of the 1st floor needs ring hanger restraints.
|
INSP-Sprinkler Rough-in/Hydro | 2/14/2005 | 2/14/2005 | 2/14/2005 | A | PART |
Troy Cobbley
|
|
|
The rest of the fourth floor and first floor is ok to cover and the standpipes are ok. Need to verify clearance around standpipe at penatrations at fourth floor, overspaced heads in the north storage rooms on second and third floors and all piping for the front drive through. 2/14/2005 9:49:48 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/25/2005 | 1/26/2005 | 1/26/2005 | A | PART |
Troy Cobbley
|
|
|
See approved plans for location on fourth floor that is ok for covering. Plans need to be resubmitted again to get approval for the piping changes at the south end of the building and the different heads in the overbuilds. 1/26/2005 11:00:34 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/24/2005 | 1/25/2005 | 1/25/2005 | P | CANC |
Troy Cobbley
|
|
|
Cancelled per message left by Scott 1/25/2005 3:49:59 PM
|
INSP-Conference | 1/19/2005 | 1/19/2005 | 1/19/2005 | P | DONE |
Troy Cobbley
|
|
|
Contractor wanted to know what I would allow for cover on the fourth floor. I went over what I would need for access. He will call me back later in the week with a definite plan for approval. 1/19/2005 3:14:12 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/12/2005 | 1/13/2005 | 1/13/2005 | A | PART |
Troy Cobbley
|
|
|
3rd floor pipe sizing has been corrected. 4th floor piping rough-in is ok. Contractor added additional sidewall heads to cover areas that are lacking coverage near sinks. Resubmittals required for these changes and the changes at the stairwells. 1/13/2005 10:43:45 AM
|
INSP-Sprinkler Rough-in | 1/6/2005 | 1/7/2005 | 1/7/2005 | P | PART |
Troy Cobbley
|
|
|
Third floor piping is ok to cover except areas marked on approved plans. 1/7/2005 2:28:49 PM
|
INSP-Conference | 12/22/2004 | 12/23/2004 | 12/23/2004 | A | DONE |
Troy Cobbley
|
|
|
Inspection called in for review of notes for possible changes. Third floor living area calcs done to 120 sq. ft.. Per Bob Knight section A14.4.4.3.3 was used for average square footage used in calcs. 12/23/2004 10:58:55 AM
|
INSP-Sprinkler Rough-in | 12/21/2004 | 12/22/2004 | 12/22/2004 | A | PART |
Troy Cobbley
|
|
|
See on site city approved plans for locations where it is ok to cover sprinkler pipingAreas include 1st, 2nd and 3rd floors. 1 1/2" piping at elevator on 1st floor has been installed as 2" and 1 1/4" piping on the second floor has been installed as 1 1/2". Resubmit plans with changes for approval prior to permit being finaled. 12/22/2004 10:27:08 AM
|
INSP-Sprinkler Rough-in/Hydro | 12/22/2004 | 12/22/2004 | 12/22/2004 | P | PASS |
Troy Cobbley
|
|
|
Hangers on 1st floor and overspaced head fixed. Piping is ok to cover as marked on approved plans. Approved plans did not include approval notes. Inspection to be called in for review of notes for possible changes. 12/22/2004 3:36:57 PM
|
INSP-Sprinkler Rough-in/Hydro | 12/21/2004 | 12/21/2004 | 12/21/2004 | P | CANC |
Rick Jackson
|
|
|
rough to cover 1 and 2 floor. Please call 1 hour prior to arrival. Thank you; Phone #: ###-#### Internet Inspection Request from: Trent Bice Rescheduled for 12/22 am 12/21/2004 4:21:54 PM
|