Permit Information
Permit NumberFIR04-00661
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 970 W RIVER ST
Project NameSPR IDAHO RECORDS MANAGEMENT
Customer Number 
ePlanReview 
Description
(IDAHO RECORDS MANAGEMENT)(IDAHO SELF STORAGE - BLDG A/B-1ST FLR) To install a Double Interlocked Preaction System in a new 710-ft/2 fire rated storage vault for multi-media and paper documents located in southwest corner of existing 33,060-ft/2 warehouse building previously protected with a shell system under FIR03-00816. This building is fully fire sprinklered for area increase. The fire sprinkler system work shall comply with the IFC 2000, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD04-01854.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/16/200412/16/200412/16/2004APASS
DetailsRick Jackson
Final okay 12/16/2004 9:48:09 AM
INSP-Final Inspection12/10/200412/10/200412/10/2004PNR
DetailsRick Jackson
Sam; Phone #: ###-#### Internet Inspection Request from: Jan Rice Alarm system not ready to test pre-action system 12/10/2004 2:58:57 PM
INSP-Sprinkler Rough-in/Hydro12/7/200412/8/200412/8/2004PFAIL
DetailsRick Jackson
air test 40 psi completion at 2 pm//// Pressure dropped to 37 psi; will need to retest 12/8/2004 2:52:19 PM
INSP-Sprinkler Rough-in/Hydro12/7/200412/7/200412/7/2004PPART
DetailsRick Jackson
Started air test at 2 pm with 40 psi on preaction system 12/7/2004 3:35:25 PM
INSP-Sprinkler Rough-in/Hydro11/10/200411/10/200411/10/2004PPART
DetailsRick Jackson
Adam-; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner hydro okay; the air line from the compressor had a small drip and will need to be replaced to complete the 24 hr air test 11/10/2004 3:43:32 PM
INSP-Sprinkler Rough-in/Hydro11/8/200411/9/200411/9/2004PFAIL
DetailsRick Jackson
1:30 pm - finish air test 42 psi at start Air test failed - dropped pressure 11/9/2004 2:01:15 PM
INSP-Sprinkler Rough-in11/8/200411/8/200411/8/2004PPART
DetailsRick Jackson
Adam; Phone #: ###-#### Internet Inspection Request from: Jan Rice Start 24 hour air test at 42 psi; Model G 212 heads used instead of Reliable F1FR QR heads - TVFP shows same K factor 11/8/2004 1:56:43 PM