INSP-Final Inspection | 7/13/2005 | 7/14/2005 | 7/14/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Final Inspection | 7/8/2005 | 7/8/2005 | 7/8/2005 | P | PART |
Forrest France
|
|
|
Need ceiling tile installed at head locations and escutcheons on prior to final, provide NFPA 25, provide signs for auxillary drains.
|
INSP-Final Inspection | 7/6/2005 | 7/7/2005 | 7/7/2005 | A | FAIL |
Forrest France
|
|
|
Repair outside bell, perform forward flow test, provide heads, head wrench, and NFPA 25 in head box, provide sinage on all valves in riser room, install ceiling tile and canopies prior to final.
|
INSP-Final Inspection | 7/1/2005 | 7/1/2005 | 7/1/2005 | P | PART |
Forrest France
|
|
|
Overhead hydro test passed, rough-in is good for cover. Need alarms and forward flow tesing prior to final.
|
INSP-Sprinkler Rough-in/Hydro | 6/24/2005 | 6/27/2005 | 6/27/2005 | P | FAIL |
Forrest France
|
|
|
Attatch retaining strap at hanger first floor nw corner, provide flexible coupling at 4" main where it passes through floor slab, provide retaining nuts on sammy screws at 2nd floor trapeze hangers, provide plans showing upright heads above exterior canopy west side, upright heads at some locations in shell areas 1st and 2nd floors are blocked by truss webs, TI demising walls, and plumbing pipe.
|
INSP-Supply line flush | 6/14/2005 | 6/16/2005 | 6/16/2005 | A | PART |
Forrest France
|
|
|
Underground fire supply line hydro and flush both passed inspection.
|
INSP-Sprinkler Rough-in | 5/19/2005 | 5/20/2005 | 5/20/2005 | A | CANC |
Forrest France
|
|
|
Cancel inspection per. Tom Easton at Grinnell. Duplicate inspection, this inspection already completed the previous day.
|
INSP-Conference | 5/19/2005 | 5/19/2005 | 5/19/2005 | P | DONE |
Forrest France
|
|
|
On site discussion with Tom Easton of Grinnell regarding sprinkler coverage requirements in concealled spaces above awning. Spoke with Bill Alexander regarding this issue and concluded sprinklers are required.
|
INSP-Sprinkler Rough-in | 5/19/2005 | 5/19/2005 | 5/19/2005 | P | CANC |
Forrest France
|
|
|
please call 30 min prior to inspection//tom; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa///cancel per tom easton 5/19/05 12:20pm BAS
|
INSP-Sprinkler Rough-in | 5/19/2005 | 5/19/2005 | 5/19/2005 | P | PART |
Forrest France
|
|
|
Underground fire supply line stub out OK to cover.
|
INSP-Sprinkler Rough-in | 5/10/2005 | 5/11/2005 | 5/11/2005 | A | FAIL |
Forrest France
|
|
|
Overhead pipe installed does not match piping plan on approved drawings in front entry or 2nd floor main/branch line connections. Re-submit plans reflecting all field changes.
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2005 | 5/11/2005 | 5/11/2005 | A | FAIL |
Forrest France
|
|
|
Underground fire supply main does not meet min. 4'-6" depth of bury requirements. Provide sleeve for EQ clearance through floor slab at riser. Cover bolts at MJ 90.
|
INSP-Sprinkler Rough-in | 4/11/2005 | 4/11/2005 | 4/11/2005 | P | FAIL |
Troy Cobbley
|
|
|
Could not find plans to do the inspection
|
INSP-Sprinkler Rough-in | 4/7/2005 | 4/8/2005 | | A | |
|
|
|
mick Note: cover underground; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|