Permit Information
Permit NumberFIR05-00052
StatusFinaled
Name PROTEX
Site Address 121 N 9TH ST
Project Namealm - PLAZA 121
Customer Number 
ePlanReview 
Description
The data has been moved to a Word document attached to this case.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/18/20064/18/20064/18/2006PPASS
DetailsForrest France
Fire alarm passed final inspection, alarm permit finaled.
INSP-Final Inspection4/14/20064/17/20064/17/2006APART
DetailsForrest France
Inspection for elevator recall/shutdown at three elevators performed today, need to provide missing SD at elevator lobby 1st floor resturant as indicated on plans, contractor to request related shell alarm permits for final at next inspection.
INSP-Final Inspection4/13/20064/14/20064/14/2006ACANC
DetailsForrest France
This inspection is to demonstrate elevator recall in upgraded elevators, please do inspection as close to 8:00 A.M. as possible Internet Inspection Request from: Terry Owsley Inspection cancelled from web by: Terry Owsley
INSP-Alarm Testing5/20/20055/20/20055/20/2005PPART
DetailsForrest France
Farmers and Merchants bank spaces in basement, first, and second floors passed fire alarm inspection. Revised plans need to reflect additional HS in basement elevator lobby, actual location of heat pump in men's room, correct cd of HS in first floor office.
INSP-Final Inspection4/22/20054/22/20054/22/2005PPART
DetailsTroy Cobbley
A temporary occupancy was given for the second floor. The fire alarm system passed in the finished areas. The area to the south of the new lobby is unfinished and will require a separate FIR permit if not finished by the time the building is finaled
INSP-Final Inspection2/28/20053/1/20053/1/2005APART
DetailsTroy Cobbley
Temporary occupancy given. Fire alarm panel and NAC panels inspected. Duct detectors on the sixth floor inspected. Induct detectors at main supply and returns on first through sixth floor inspected. Pull stations on all floors inspected. Audio visuals on sixth floor and first floor lobby inspected. Individual a/v's on first through sixth and basement inspected. All sprinkler monitoring points inspected. All other items not inspected. Plans will need to be resubmitted with changes which include ceiling mounted a/v's, deletion of pull on sixth floor, additional heat in penthouse and relocated NAC panels. 3/1/2005 2:53:50 PM
INSP-Final Inspection2/28/20052/28/20052/28/2005PFAIL
DetailsTroy Cobbley