INSP-Final Inspection | 7/6/2005 | 7/6/2005 | 7/6/2005 | A | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Final Inspection | 7/1/2005 | 7/1/2005 | 7/1/2005 | P | PART |
Forrest France
|
|
|
Need to install two escutcheons on heads in the kitchen area.
|
INSP-Final Inspection | 6/13/2005 | 6/13/2005 | 6/13/2005 | P | PART |
Forrest France
|
|
|
Remainder of rough-in at kitchen area OK to cover. Need ceiling tile installed at heads, foreward flow and alarms for final.
|
INSP-Final Inspection | 5/10/2005 | 5/11/2005 | 5/11/2005 | A | PART |
Forrest France
|
|
|
Rough-in above hard lid areas first floor cafe OK to cover. Grid ceiling and heads in grid ceiling areas not installed yet. Verify wood 2x4's above hard lid at south soffit are fire treated.
|
INSP-Sprinkler Rough-in/Hydro | 5/10/2005 | 5/10/2005 | 5/10/2005 | P | FAIL |
Forrest France
|
|
|
Hanger on 1" arm over at end of 2" main, north side, is not within 2' of the end. Pendent head in soffit hard lid at corner is not installed as shown on plan. EQ brace on relocated 2 1/2" main is not installed on the last piece of main as shown on plan.
|
INSP-Sprinkler Rough-in/Hydro | 3/4/2005 | 3/7/2005 | 3/7/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire sprinklers ok to cover above hard lids 3/7/2005 9:06:40 AM
|