INSP-Final Inspection | 4/22/2005 | 4/22/2005 | 4/22/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinkler finaled
|
INSP-Final Inspection | 4/21/2005 | 4/21/2005 | 4/21/2005 | P | FAIL |
Forrest France
|
|
|
Perform foreward flow test. Provide chain and lock for wall post indicator.
|
INSP-Final Inspection | 4/19/2005 | 4/20/2005 | 4/20/2005 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled per contractor
|
INSP-Sprinkler Rough-in/Hydro | 4/15/2005 | 4/18/2005 | 4/18/2005 | P | PART |
Forrest France
|
|
|
Overhead sprinkler rough-in OK to cover, need calc. verification on 3 inch main offset at south end, need psi relief at riser for grid system.
|
INSP-Final Inspection | 4/15/2005 | 4/18/2005 | 4/18/2005 | A | CANC |
Troy Cobbley
|
|
|
###-#### Jim Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 4/18/2005 | 4/18/2005 | 4/18/2005 | P | PASS |
Forrest France
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/15/2005 | 4/15/2005 | 4/15/2005 | P | CANC |
Forrest France
|
|
|
###-#### Jim Cancel inspection per. Jim Danes, not ready - will re-schedule next week.
|
INSP-Sprinkler Rough-in/Hydro | 3/31/2005 | 4/1/2005 | 4/1/2005 | A | FAIL |
Forrest France
|
|
|
Review notes have not been address. See items for trapeze and tail back pipe sizing
|