INSP-Final Inspection | 2/5/2007 | 2/5/2007 | 2/5/2007 | P | PASS |
Forrest France
|
|
|
UG fire supply line permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2006 | 3/3/2006 | 3/3/2006 | A | DEFR |
Forrest France
|
|
|
Wrong permit number called in, was intended for a pump test on the overhead, noted that the sensing lines are incorrectly piped.
|
INSP-Sprinkler Rough-in/Hydro | 1/3/2006 | 1/4/2006 | 1/4/2006 | P | PART |
Forrest France
|
|
|
Hydrostatic test for the UG fire supply line passed inspection.
|
INSP-Supply line flush | 12/30/2005 | 1/3/2006 | 1/3/2006 | P | NR |
Forrest France
|
|
|
UG hydrostatic test not ready as the guage was below 200 psi at the begining of the test.
|
INSP-Sprinkler Rough-in/Hydro | 6/9/2005 | 6/9/2005 | 6/9/2005 | P | PART |
Forrest France
|
|
|
The remainder of underground fire supply line is OK to cover.
|
INSP-Sprinkler Rough-in | 6/7/2005 | 6/7/2005 | 6/7/2005 | P | PART |
Forrest France
|
|
|
Underground fire supply line OK for cover to last column line K northwest corner of hotel.
|
INSP-Sprinkler Rough-in | 6/6/2005 | 6/6/2005 | 6/6/2005 | P | PART |
Forrest France
|
|
|
Underground fire supply line OK to cover up to point installed at 3rd column line from north side of hotel.
|
INSP-Sprinkler Rough-in/Hydro | 6/3/2005 | 6/3/2005 | 6/3/2005 | P | PART |
Forrest France
|
|
|
Underground supply line OK to cover up to installed point just past vault.
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2005 | 6/2/2005 | 6/2/2005 | A | PART |
Forrest France
|
|
|
The two lengths of 8'' C-900 installed from thrust block at stub in are OK to cover.
|
INSP-Sprinkler Rough-in/Hydro | 4/13/2005 | 4/13/2005 | 4/13/2005 | P | PASS |
Forrest France
|
|
|
Underground stub-in OK to cover.
|