TRINITY PRESBYTERIAN CHURCH * To install a complete wet, Light Hazard fire sprinkler system in a new 28,556-ft/2, one story Type III-B church and Group I-4 daycare (118 children) building. Fire sprinklers are used for area. Underground fire service supply was installed under FIR05-00016. The overhead fire sprinkler system work shall comply with the IFC 2000, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD04-01909.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/26/20058/29/20058/29/2005APASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Final Inspection8/26/20058/26/20058/26/2005PCANC
DetailsForrest France
This re-inspection is cancelled due to time constraints.
INSP-Final Inspection8/25/20058/26/20058/26/2005AFAIL
DetailsForrest France
The flow switch failed to function under test conditions, provide forward flow test, provide "911 sign" at outside bell, install all escutcheons.
INSP-Sprinkler Rough-in8/17/20058/17/20058/18/2005PFAIL
DetailsForrest France
Hanger in nursery room 127 needs retaining strap attatched, head in corridor outside room 127 needs a hanger installed on the armover. All remaining areas are okay to cover.
INSP-Sprinkler Rough-in/Hydro8/11/20058/12/20058/12/2005PPASS
DetailsTroy Cobbley
Above ground hydro test passed. Contractor needs to provide test papers that have been filled out. I signed for the hydro test.
INSP-Sprinkler Rough-in/Hydro8/10/20058/11/20058/11/2005PFAIL
DetailsTroy Cobbley
Overhead hydro test failed. System lost 4 lbs
INSP-Sprinkler Rough-in/Hydro8/2/20058/5/20058/5/2005PPART
DetailsForrest France
Attatch retaining straps to beam in nursery area 127, provide approved hanger for 11/4 pipe in hallway 108, adjust DSW at closet 163, inspect lines not yet installed at west end of sanctuary, verify final head locations after drops are cut in, all remaining areas are okay to cover.
INSP-Conference6/16/20056/17/20056/17/2005ADONE
DetailsForrest France
Discussed location of FDC to meet requirements of NFPA 13 8.16.2.4.6.
INSP-Sprinkler Rough-in6/14/20056/14/20056/14/2005PFAIL
DetailsForrest France
Pendent heads in kitchen at range hood need to be proper temp. rating, need dry SW at closet 163 as shown on plans, attatch retaining straps in rooms 123 and 127, head in hall 108 is overspaced, provide aux. drain at trapped 4" main in sanctuary, upright head in mezz. SE corner is overspaced, hangers overspaced on last pcs. in multi-purpose room, FDC must meet requirements of note #25 on plan review.
INSP-Sprinkler Rough-in4/26/20054/27/20054/27/2005PCANC
DetailsForrest France
Approved plans not available for review. Contractor to re-schedule inspection.