INSP-Final Inspection | 8/26/2005 | 8/29/2005 | 8/29/2005 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/26/2005 | 8/26/2005 | 8/26/2005 | P | CANC |
Forrest France
|
|
|
This re-inspection is cancelled due to time constraints.
|
INSP-Final Inspection | 8/25/2005 | 8/26/2005 | 8/26/2005 | A | FAIL |
Forrest France
|
|
|
The flow switch failed to function under test conditions, provide forward flow test, provide "911 sign" at outside bell, install all escutcheons.
|
INSP-Sprinkler Rough-in | 8/17/2005 | 8/17/2005 | 8/18/2005 | P | FAIL |
Forrest France
|
|
|
Hanger in nursery room 127 needs retaining strap attatched, head in corridor outside room 127 needs a hanger installed on the armover. All remaining areas are okay to cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/11/2005 | 8/12/2005 | 8/12/2005 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed. Contractor needs to provide test papers that have been filled out. I signed for the hydro test.
|
INSP-Sprinkler Rough-in/Hydro | 8/10/2005 | 8/11/2005 | 8/11/2005 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test failed. System lost 4 lbs
|
INSP-Sprinkler Rough-in/Hydro | 8/2/2005 | 8/5/2005 | 8/5/2005 | P | PART |
Forrest France
|
|
|
Attatch retaining straps to beam in nursery area 127, provide approved hanger for 11/4 pipe in hallway 108, adjust DSW at closet 163, inspect lines not yet installed at west end of sanctuary, verify final head locations after drops are cut in, all remaining areas are okay to cover.
|
INSP-Conference | 6/16/2005 | 6/17/2005 | 6/17/2005 | A | DONE |
Forrest France
|
|
|
Discussed location of FDC to meet requirements of NFPA 13 8.16.2.4.6.
|
INSP-Sprinkler Rough-in | 6/14/2005 | 6/14/2005 | 6/14/2005 | P | FAIL |
Forrest France
|
|
|
Pendent heads in kitchen at range hood need to be proper temp. rating, need dry SW at closet 163 as shown on plans, attatch retaining straps in rooms 123 and 127, head in hall 108 is overspaced, provide aux. drain at trapped 4" main in sanctuary, upright head in mezz. SE corner is overspaced, hangers overspaced on last pcs. in multi-purpose room, FDC must meet requirements of note #25 on plan review.
|
INSP-Sprinkler Rough-in | 4/26/2005 | 4/27/2005 | 4/27/2005 | P | CANC |
Forrest France
|
|
|
Approved plans not available for review. Contractor to re-schedule inspection.
|