INSP-Final Inspection | 3/8/2006 | 3/14/2006 | 3/14/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 12/22/2005 | 12/22/2005 | 12/22/2005 | P | FAIL |
Troy Cobbley
|
|
|
Need to test recall for elevator, flow switches need readjusted on the east and west systems, test duct detectors, change signals to 4/2 format, finish reviewing notes.
|
INSP-Final Inspection | 10/7/2005 | 10/10/2005 | 10/10/2005 | A | FAIL |
Troy Cobbley
|
|
|
Only tested the phone lines and three tamper switches. Phone lines had to be repaired as I waited. A meter had to be found for testing batteries but it didn't work. The supervisory points received at the central station do not match plans. Need to test all devices. Need security to the outlet on same circuti to the facp.
|
INSP-Final Inspection | 10/7/2005 | 10/7/2005 | 10/7/2005 | P | CANC |
Forrest France
|
|
|
Inspection to be rescheduled for monday the 10th per agreement with Rick Jackson. Sufficient information to determine what has and has not been tested is not available to a degree that is comfortable for verification without being familiar with the project history. This inspection to be defered to Troy Cobbley per request by Forrest.
|
FIR-Aging Inspection | 10/4/2005 | 10/4/2005 | 10/6/2005 | | NR |
Troy Cobbley
|
|
|
Per Rick Jackson work is in progress.
|