INSP-Final Inspection | 10/13/2005 | 10/13/2005 | 10/13/2005 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 10/13/2005 | 10/13/2005 | 10/13/2005 | P | PASS |
Troy Cobbley
|
|
|
Varsity Bar and Grill sprinkler permit finaled
|
INSP-Final Inspection | 10/7/2005 | 10/7/2005 | 10/7/2005 | P | PART |
Forrest France
|
|
|
Final pending installation of ceiling tile and escutcheons.
|
INSP-Sprinkler Rough-in/Hydro | 9/23/2005 | 9/26/2005 | 9/26/2005 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed inspection, main tie in is satisfactory, not all drops are cut in at this time.
|
INSP-Final Inspection | 9/23/2005 | 9/23/2005 | 9/23/2005 | P | CANC |
Forrest France
|
|
|
Hydrostatic test rescheduled for monday the 26th per agreement with Brian of TV sprinkler.
|
INSP-Sprinkler Rough-in | 8/2/2005 | 8/3/2005 | 8/3/2005 | P | PART |
Forrest France
|
|
|
Need to add one upright head in area overspaced at southeast corner, need to verify 3" main connection and EQ brace at last piece of main when installed, all remaining areas are good for cover.
|