Permit Information
Permit NumberFIR05-00429
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 3201 W AIRPORT WAY
Project NameSPR BOISE VARSITY BAR & GRILLE
Customer Number 
ePlanReview 
Description
(MCDONALDS - BOISE AIR TERMINAL - FOOD COURT) To add by redesign and install a OH-2 extended pipe protected area for a new 1,842-ft/2 restaurant tenant space, located in the southeast corner of "Original Concourse B" at the Boise Air Terminal. The former restaurant tenant spaces at this location will be demolished. Fire sprinkler work is related to the installation of interior nonbearing walls, suspended acoustical ceilings with gypsum board soffits. This building is fire sprinklered to substitute for 1-hr fire-resistive construction. This fire protection work shall comply with the IFC 2003 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of meeting minimum fire protection code. This permit is attached to BLD05-004487.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/13/200510/13/200510/13/2005PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection10/13/200510/13/200510/13/2005PPASS
DetailsTroy Cobbley
Varsity Bar and Grill sprinkler permit finaled
INSP-Final Inspection10/7/200510/7/200510/7/2005PPART
DetailsForrest France
Final pending installation of ceiling tile and escutcheons.
INSP-Sprinkler Rough-in/Hydro9/23/20059/26/20059/26/2005APART
DetailsForrest France
Overhead hydrostatic test passed inspection, main tie in is satisfactory, not all drops are cut in at this time.
INSP-Final Inspection9/23/20059/23/20059/23/2005PCANC
DetailsForrest France
Hydrostatic test rescheduled for monday the 26th per agreement with Brian of TV sprinkler.
INSP-Sprinkler Rough-in8/2/20058/3/20058/3/2005PPART
DetailsForrest France
Need to add one upright head in area overspaced at southeast corner, need to verify 3" main connection and EQ brace at last piece of main when installed, all remaining areas are good for cover.