INSP-Final Inspection | 1/4/2006 | 1/5/2006 | 1/5/2006 | A | PASS |
Forrest France
|
|
|
Fire sprinkler passed final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 1/3/2006 | 1/4/2006 | 1/4/2006 | A | PASS |
Troy Cobbley
|
|
|
wet and dry system hydro tests passed
|
INSP-Sprinkler Rough-in/Hydro | 11/8/2005 | 11/8/2005 | 11/8/2005 | P | PART |
Forrest France
|
|
|
Overhead sprinkler rough-in is acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 10/24/2005 | 10/25/2005 | 10/25/2005 | P | PASS |
Troy Cobbley
|
|
|
24 hour hydro test passed. Sprinkler rough-in for the southwest dry system (area above insulation) passed.
|
INSP-Supply line flush | 10/18/2005 | 10/18/2005 | 10/18/2005 | P | PART |
Forrest France
|
|
|
This inspection was for the associated UG permit FIR05-00355 to flush the supply line.
|
INSP-Sprinkler Rough-in/Hydro | 10/17/2005 | 10/17/2005 | 10/17/2005 | P | PART |
Forrest France
|
|
|
Inspected outside soffit, concealed areas below stairs, hard lid areas 2nd floor, attic dry system 1st floor east and 2nd floor, provide coverage for concealed combustible mechanical shafts, provide restraint for sprig-ups over 4' in length.
|