Permit Information
Permit NumberFIR05-00449
StatusFinaled
Name NORTHWEST SALES COMPANY
Site Address 950 W BANNOCK ST
Project Namealm - 10TH & BANNOCK
Customer Number 
ePlanReview 
Description
To provide a required manual fire alarm system that includes sprinkler monitoring, fire pump/tank monitoring, elevator recall/shutdown, HVAC shutdown, fire/smoke damper control, door release, required automatic detection, fire department communication system and voice/evac notification throughout. The stairwells are pressurized utilizing supply fans on the roof with fire/smoke dampers that "fail open". 3/12/2006 - Only one fan has a damper, it has been changed to a "fire" damper only.

The associated building permit (BLD 04-02348) is to construct a new 182,950 square foot, twelve story concrete and steel framed office and retail, high rise shell and core building and related site improvements. This is a shell and core building only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. The core work to be completed under this permit includes the following: 1st floor - 15,640 sq. ft. The entire first floor, with the exception of the two retail tenant spaces, will be finished under this permit. 2nd floor (intermediate floor) - 6,310 sq. ft. - Open storage floor. 3rd floor - 16,200 sq. ft. The restrooms, corridors, elevator lobbies, conference center and break room will be finished under this permit. 4th thru 12th floors - 16,200 sq. ft. (each floor level) - The restrooms and elevator lobbies will be finished under this permit. There is a recorded ground and air rights agreement between the 10th and Bannock property, the property to the north and the City of Boise. The purpose of this agreement is relocate the assumed property line at the alley to 10'-6" from the 10th and Bannock north property line and to restrict the maximum building height on the north property to 60'-0". This agreement is for the purpose of determining the fire-resistive exterior wall and opening protection requirements for the north exterior wall of the new 10th and Bannock building. All construction per the approved plans and attached comment list. (Grading, Drainage and Foundation permitted under BLD04-01632) JCM 10th & Bannock Building (Shell & Core )
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/28/20064/28/20064/28/2006PPASS
DetailsForrest France
Added devices at the top of elevator hoistway tested, updated map verified, covers at SD removed, alarm passed final field inspection, permit finaled.
INSP-Alarm Testing4/25/20064/25/20064/26/2006PDEFR
DetailsForrest France
Inspection to be scheduled 4/27 per agreement.
INSP-Alarm Testing4/23/20064/24/20064/24/2006APASS
DetailsForrest France
Fire alarm work passed final inspection, permit finaled.
INSP-Alarm Testing4/19/20064/20/20064/20/2006APART
DetailsForrest France
Tested elevator machine room, elevator shutdown/recall, FACP, phone lines, battery, obtained signal verifications. Need to provide firemans phones, remove all remaining covers at SD, add FJ at the penthouse stair landing, and provide updated map at the panel prior to final approval. Some items regarding section 509 of the IFC for the command center still need addressed including item #4, #10 and min. ft2 of the room.
INSP-Alarm Testing4/17/20064/18/20064/18/2006APART
DetailsForrest France
Elevator recall at floors 1-11 tested today, FD communication system intercom and phone jacks on floors 1-11 tested, voice evac re-tested on all floors, phase reversal monitoring for fire pump verified, added SD at lobby tested. Elevator machine room, elevator shutdown, main FACP, command center items per IFC, map at panel, and signal verification not inspected at this time.
INSP-Alarm Testing4/16/20064/17/20064/17/2006ACANC
DetailsForrest France
Cancel inspection per contractor due to job site conditions.
INSP-Alarm Testing4/10/20064/14/20064/14/2006APART
DetailsForrest France
All fire sprinkler monitoring points including tampers, flows, tank and pump supervision tested today, main riser flow and tamper point corrected while on site, re-tested west stair fan for functionality on alarm, voice evac failed to function on alarm at the 6th, 10th and 11th floors today-have incurred problems with intermittent failure of the voice system on three separate inspections during this project.
INSP-Alarm Testing4/10/20064/13/20064/13/2006APART
DetailsForrest France
Tested ground level smoke detectors at lobby area, need to provide one additional SD above front entrance as coverage is obstructed by beam blockage, fire alarm wire shall be attatched to the building structure, tested notification and detection devices at the mechanical penthouse, the west stair fan was not functional for testing, tested all air handling units in the fan rooms on floors 3 through 11, need to provide dates on NAC batteries at 6th and 8th floors, sprinkler monitoring to be tested at next inspection.
INSP-Alarm Testing4/10/20064/12/20064/13/2006APART
DetailsForrest France
Tested detection and notification devices on floors 7 through 11, air handlers in the fan rooms were not in condition to be tested, firemans phone jacks and elevator lobbies not tested at this inspection, voice evac re-tested for functionality at the 6th floor, need to date batteries at the 6th and 8th floor nac panels.
INSP-Alarm Testing4/10/20064/11/20064/11/2006AFAIL
DetailsForrest France
Detection and notification devices tested on the 5th and 6th floors today, voice evac failed to function properly, ID, SD and manual pulls tested okay, need to date batteries in the 6th floor nac panel, elevator lobby smokes not tested at this time.
INSP-Alarm Testing4/7/20064/10/20064/10/2006APART
DetailsForrest France
Tested detection and notification devices on the 3rd and 4th floors, HVAC units were not in a condition to be tested in the fan rooms, missing mag door holder at the 3rd floor north double doors (door release not verified), checked audibility in the fan room on 2nd floor, previous c/n items are satisfactory, discussed inspection schedule for the remainder of this project with D. Maxwell.
INSP-Alarm Testing4/6/20064/7/20064/7/2006AFAIL
DetailsForrest France
Two pull station addresses on the ground level are switched (#41 and 42), need to relocate one SD min. 3' away from HVAC supply diffuser in the corridor, audibility has been adjusted to the appropriate level in the mech. mezz as required, tested notification and detection devices on the ground level, 8 SD above the lobby not tested at this time due to access issues.
INSP-Alarm Testing4/4/20064/6/20064/6/2006APART
DetailsForrest France
Partial test of detection and notification devices on the ground level, intermediate mech. mezzanine, and 2nd floors, need to verify audibility requirements are met in the mech. mezz., no sprinkler related items tested at this time.