INSP-Final Inspection | 4/28/2006 | 4/28/2006 | 4/28/2006 | P | PASS |
Forrest France
|
|
|
Added devices at the top of elevator hoistway tested, updated map verified, covers at SD removed, alarm passed final field inspection, permit finaled.
|
INSP-Alarm Testing | 4/25/2006 | 4/25/2006 | 4/26/2006 | P | DEFR |
Forrest France
|
|
|
Inspection to be scheduled 4/27 per agreement.
|
INSP-Alarm Testing | 4/23/2006 | 4/24/2006 | 4/24/2006 | A | PASS |
Forrest France
|
|
|
Fire alarm work passed final inspection, permit finaled.
|
INSP-Alarm Testing | 4/19/2006 | 4/20/2006 | 4/20/2006 | A | PART |
Forrest France
|
|
|
Tested elevator machine room, elevator shutdown/recall, FACP, phone lines, battery, obtained signal verifications. Need to provide firemans phones, remove all remaining covers at SD, add FJ at the penthouse stair landing, and provide updated map at the panel prior to final approval. Some items regarding section 509 of the IFC for the command center still need addressed including item #4, #10 and min. ft2 of the room.
|
INSP-Alarm Testing | 4/17/2006 | 4/18/2006 | 4/18/2006 | A | PART |
Forrest France
|
|
|
Elevator recall at floors 1-11 tested today, FD communication system intercom and phone jacks on floors 1-11 tested, voice evac re-tested on all floors, phase reversal monitoring for fire pump verified, added SD at lobby tested. Elevator machine room, elevator shutdown, main FACP, command center items per IFC, map at panel, and signal verification not inspected at this time.
|
INSP-Alarm Testing | 4/16/2006 | 4/17/2006 | 4/17/2006 | A | CANC |
Forrest France
|
|
|
Cancel inspection per contractor due to job site conditions.
|
INSP-Alarm Testing | 4/10/2006 | 4/14/2006 | 4/14/2006 | A | PART |
Forrest France
|
|
|
All fire sprinkler monitoring points including tampers, flows, tank and pump supervision tested today, main riser flow and tamper point corrected while on site, re-tested west stair fan for functionality on alarm, voice evac failed to function on alarm at the 6th, 10th and 11th floors today-have incurred problems with intermittent failure of the voice system on three separate inspections during this project.
|
INSP-Alarm Testing | 4/10/2006 | 4/13/2006 | 4/13/2006 | A | PART |
Forrest France
|
|
|
Tested ground level smoke detectors at lobby area, need to provide one additional SD above front entrance as coverage is obstructed by beam blockage, fire alarm wire shall be attatched to the building structure, tested notification and detection devices at the mechanical penthouse, the west stair fan was not functional for testing, tested all air handling units in the fan rooms on floors 3 through 11, need to provide dates on NAC batteries at 6th and 8th floors, sprinkler monitoring to be tested at next inspection.
|
INSP-Alarm Testing | 4/10/2006 | 4/12/2006 | 4/13/2006 | A | PART |
Forrest France
|
|
|
Tested detection and notification devices on floors 7 through 11, air handlers in the fan rooms were not in condition to be tested, firemans phone jacks and elevator lobbies not tested at this inspection, voice evac re-tested for functionality at the 6th floor, need to date batteries at the 6th and 8th floor nac panels.
|
INSP-Alarm Testing | 4/10/2006 | 4/11/2006 | 4/11/2006 | A | FAIL |
Forrest France
|
|
|
Detection and notification devices tested on the 5th and 6th floors today, voice evac failed to function properly, ID, SD and manual pulls tested okay, need to date batteries in the 6th floor nac panel, elevator lobby smokes not tested at this time.
|
INSP-Alarm Testing | 4/7/2006 | 4/10/2006 | 4/10/2006 | A | PART |
Forrest France
|
|
|
Tested detection and notification devices on the 3rd and 4th floors, HVAC units were not in a condition to be tested in the fan rooms, missing mag door holder at the 3rd floor north double doors (door release not verified), checked audibility in the fan room on 2nd floor, previous c/n items are satisfactory, discussed inspection schedule for the remainder of this project with D. Maxwell.
|
INSP-Alarm Testing | 4/6/2006 | 4/7/2006 | 4/7/2006 | A | FAIL |
Forrest France
|
|
|
Two pull station addresses on the ground level are switched (#41 and 42), need to relocate one SD min. 3' away from HVAC supply diffuser in the corridor, audibility has been adjusted to the appropriate level in the mech. mezz as required, tested notification and detection devices on the ground level, 8 SD above the lobby not tested at this time due to access issues.
|
INSP-Alarm Testing | 4/4/2006 | 4/6/2006 | 4/6/2006 | A | PART |
Forrest France
|
|
|
Partial test of detection and notification devices on the ground level, intermediate mech. mezzanine, and 2nd floors, need to verify audibility requirements are met in the mech. mezz., no sprinkler related items tested at this time.
|