INSP-Final Inspection | 12/20/2005 | 12/21/2005 | 12/21/2005 | A | PASS |
Forrest France
|
|
|
Required correction has been completed, fire sprinkler permit finaled.
|
INSP-Final Inspection | 12/15/2005 | 12/16/2005 | 12/16/2005 | A | PART |
Forrest France
|
|
|
All items are satisfactory except an obstructed head in the 2nd level bonus room is blocked by a surface mounted light, final pending relocation of light fixture or relocate head.
|
INSP-Final Inspection | 12/14/2005 | 12/15/2005 | 12/15/2005 | P | CANC |
Troy Cobbley
|
|
|
Jonathan is the contact @ ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
INSP-Final Inspection | 12/2/2005 | 12/5/2005 | 12/5/2005 | A | CANC |
Troy Cobbley
|
|
|
Per Jonathan job is not ready for inspection
|
INSP-Sprinkler Rough-in | 9/2/2005 | 9/6/2005 | 9/6/2005 | A | PART |
Forrest France
|
|
|
Overhead piping is okay to cover, field changes in pipe routing from approved plans are okay to show on as-builts per Bill Alexander, one SW has been added in the garage and one head added in low soffit in front of utility room, discussed with contractor possible light fixture obstruction to sprinkler head in first floor bedroom.
|
INSP-Sprinkler Rough-in | 9/2/2005 | 9/2/2005 | 9/2/2005 | P | CANC |
Forrest France
|
|
|
No time for this inspection today, spoke with Jonathan to schedule for next week per our conversation.
|
INSP-Supply line flush | 8/24/2005 | 8/25/2005 | 8/25/2005 | P | PART |
Forrest France
|
|
|
UG flush is satisfactory.
|