INSP-Final Inspection | 12/7/2005 | 12/7/2005 | 12/7/2005 | P | PASS |
Forrest France
|
|
|
Defficient items have been corrected, fire sprinkler passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 11/29/2005 | 11/30/2005 | 11/30/2005 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed, not all c/n items have been completed at this time.
|
INSP-Final Inspection | 11/22/2005 | 11/23/2005 | 11/23/2005 | A | FAIL |
Forrest France
|
|
|
The rough-in inspection failed, alarms are not connected, ceiling tile is not installed, the hydrostatic test failed due to a leaking #1 shutoff valve at the riser backflow.
|
INSP-Sprinkler Rough-in/Hydro | 11/22/2005 | 11/23/2005 | 11/23/2005 | A | FAIL |
Forrest France
|
|
|
See approved plans for areas in the office and sales floor for defficiencies including head location, temperatures, hangers, taped or painted heads, also need verification of type of plywood installed above the exterior canopy, not a complete inspection at this time.
|
INSP-Final Inspection | 11/21/2005 | 11/22/2005 | 11/22/2005 | P | CANC |
Forrest France
|
|
|
No time available for this inspection today.
|
INSP-Sprinkler Rough-in/Hydro | 11/21/2005 | 11/22/2005 | 11/22/2005 | P | CANC |
Forrest France
|
|
|
No time for this inspection today.
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2005 | 11/22/2005 | 11/22/2005 | A | CANC |
Forrest France
|
|
|
No time for this inspection today.
|
INSP-Sprinkler Rough-in | 10/25/2005 | 10/25/2005 | 10/25/2005 | P | PART |
Forrest France
|
|
|
Overhead rough-in at three hard lid areas in the mezzanine space appear acceptable pending verification with approved plans which are currently under review for resubmittal. Discussed with GC full height wall needed at open ceiling room, coverage under stairs, fire treated wood for flooring, antifreeze loop requirements.
|