INSP-Final Inspection | 3/10/2006 | 3/13/2006 | 3/13/2006 | A | PASS |
Forrest France
|
|
|
Three items defficient were corrected while on site (missing hanger, painted SW head and standard response head in closet), fire sprinkler permit work passed inspection.
|
INSP-Sprinkler Rough-in | 1/19/2006 | 1/20/2006 | 1/20/2006 | P | PART |
Forrest France
|
|
|
The remainder of overhead rough-in at the hard lid areas are good for cover, one head does not meet 8.6.3.2.3 as discussed.
|
INSP-Sprinkler Rough-in | 1/17/2006 | 1/18/2006 | 1/18/2006 | A | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover at hard lid soffits except at the east soffit not complete at this time, discussed slatted drop ceiling coverage, hydrostatic testing, and the requirements of NFPA 13 8.6.3.2.3.
|