INSP-Final Inspection | 3/16/2006 | 3/17/2006 | 3/17/2006 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/16/2006 | 3/16/2006 | 3/16/2006 | P | FAIL |
Troy Cobbley
|
|
|
Need pressure relief installed on the wet system and revised calcs
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2006 | 3/14/2006 | 3/14/2006 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test passed
|
INSP-Sprinkler Rough-in/Hydro | 3/13/2006 | 3/13/2006 | 3/13/2006 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test on the dry system started at 12:50 with 44psi on guage.
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2006 | 3/10/2006 | 3/10/2006 | | PASS |
Troy Cobbley
|
|
|
Wet system hydro test passed. Need copy of the test papers.
|
INSP-Sprinkler Rough-in/Hydro | 3/8/2006 | 3/9/2006 | 3/9/2006 | A | PART |
Troy Cobbley
|
|
|
200lb. hydro test for the dry system passed. Hydro test for the wet system failed. Also still need the fdc installed and hydro tested.
|
INSP-Sprinkler Rough-in/Hydro | 3/7/2006 | 3/8/2006 | 3/8/2006 | A | CANC |
|
|
|
Steve ###-####///3-8-06 Cancel because forgot to enter Assigned inspector and insp didn't register eus
|
INSP-Sprinkler Rough-in/Hydro | 1/20/2006 | 1/23/2006 | 1/23/2006 | A | PART |
Troy Cobbley
|
|
|
Restrooms as marked on the approved plans are ok to cover
|