INSP-Final Inspection | 5/18/2006 | 5/19/2006 | 5/19/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 5/10/2006 | 5/10/2006 | 5/10/2006 | P | PART |
Forrest France
|
|
|
Hangers have been relocated for attatchment to the building structure and to meet load requirements, retaining straps at beam clamps have been installed. Overhead rough-in is okay to cover.
|
INSP-Sprinkler Rough-in | 5/5/2006 | 5/8/2006 | 5/9/2006 | A | PART |
Forrest France
|
|
|
Hangers at various locations are missing retaining straps at beam clamps, several hangers for arm-overs have been attatched to 5/8 sheetrock as a means of support-need to verify the point of attatchment will support a min. 250lbs per NFPA 13.
|
INSP-Final Inspection | 4/27/2006 | 5/4/2006 | 5/4/2006 | A | FAIL |
Forrest France
|
|
|
The overhead sprinkler piping has been completely concealed prior to inspection for cover, it will be necessary to expose the installation for verification of code compliance. Also noted two heads at a confrence room which are spaced incorrectly.
|
INSP-Final Inspection | 2/21/2006 | 2/23/2006 | 2/23/2006 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler is complete and the installation is satisfactory at the 1400 ft/2 vending/break room and the 340 ft/2 smoking break room portion of this permit.
|
INSP-Conference | 1/17/2006 | 1/19/2006 | 1/19/2006 | P | DONE |
Forrest France
|
|
|
On site confrence to discuss project phasing as associated with the cafeteria lunchroom completion prior to the remainder of work under this permit scope.
|
INSP-Conference | 1/17/2006 | 1/17/2006 | 1/17/2006 | P | CANC |
Troy Cobbley
|
|
|
mitch; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|