INSP-Final Inspection | 10/30/2007 | 10/31/2007 | 11/1/2007 | A | PASS |
Forrest France
|
|
|
Fire alarm final inspection passed, permit finaled.
|
INSP-Final Inspection | 10/25/2007 | 10/26/2007 | 10/26/2007 | A | PART |
Forrest France
|
|
|
Tested remainder of the second floor devices, noted two SD installed too close to HVAC registers, door hardware at the inactive leaf at the west set of fire doors to the skybridge is not approved, corrections from the previous inspection are complete.
|
INSP-Final Inspection | 10/23/2007 | 10/25/2007 | 10/25/2007 | A | DEFR |
Forrest France
|
|
|
Scheduled for 10/26
|
INSP-Final Inspection | 10/16/2007 | 10/17/2007 | 10/17/2007 | A | CANC |
Troy Cobbley
|
|
|
Cancell per Jeff Walton
|
INSP-Final Inspection | 10/3/2007 | 10/4/2007 | 10/4/2007 | A | PART |
Forrest France
|
|
|
See plans for areas tested on the second floor, noted items in need of correction, HD at the elevator machine room tested okay.
|
INSP-Final Inspection | 8/23/2007 | 8/24/2007 | 8/24/2007 | A | PART |
Forrest France
|
|
|
1st floor fire alarm testing completed today, items remaining for the 1st floor include lacking HD at the elevator machine room and missing main FACP door.
|
INSP-Final Inspection | 8/21/2007 | 8/23/2007 | 8/23/2007 | A | CANC |
Forrest France
|
|
|
No time available to complete this inspection today, rescheduled for 8/24 AM as agreed.
|
INSP-Final Inspection | 8/14/2007 | 8/16/2007 | 8/16/2007 | A | PART |
Forrest France
|
|
|
Retested items on the first floor in need of correction, doors need adjusted at the service elevator lobby, missing a HD for the elevator machine room, two SD at the link relocated while on site, several items remain to be tested at the 2nd floor.
|
INSP-Final Inspection | 8/7/2007 | 8/9/2007 | 8/9/2007 | A | DEFR |
Forrest France
|
|
|
No time to complete this inspection today, rescheduled as discussed.
|
INSP-Alarm Testing | 6/27/2007 | 6/29/2007 | 7/2/2007 | A | FAIL |
Forrest France
|
|
|
SD's as installed in the electrical room, comm. room, and loading dock area do not meet spacing requirements due to structural beam blockage, missing one SD at a vestibule, visible notification is blocked at some areas in the pyro lab, duct detectors and vesdas tested okay on the first floor, noted corrections from the previous visit have been completed.
|
INSP-Sprinkler Rough-in/Hydro | 6/8/2007 | 6/13/2007 | 6/13/2007 | A | PART |
Forrest France
|
|
|
Tested a/v notification in the cleanroom areas-noted lacking coverage and overspaced devices at some locations, tested FACP batteries, AC loss, smoke at panel, manual pull stations for the basement and 1st floor tested okay, verified corrections at the basement from previous visit.
|
INSP-Final Inspection | 6/6/2007 | 6/7/2007 | 6/7/2007 | A | CANC |
Forrest France
|
|
|
No time available for this inspection today.
|
INSP-Final Inspection | 6/5/2007 | 6/6/2007 | 6/6/2007 | A | CANC |
Troy Cobbley
|
|
|
Forrest, pls call when on your way. JB needs about a 30 min notice. Phone #: ###-#### Internet Inspection Request from: Rob Puckett Inspection cancelled from web by: Rob Puckett
|
INSP-Alarm Testing | 5/29/2007 | 5/31/2007 | 5/31/2007 | A | PART |
Forrest France
|
|
|
Walk through testing of a/v notification at the 1st , 2nd and basement floor levels only completed today, noted one horn to be replaced in the basement, some areas on the first and second floors appear to be overspaced or obstructed as noted, as-built plans need to accurately reflect locations of all devices, the 1st floor pyro room may need an additional horn, clean room areas on the 1st floor remain to be verified for a/v testing due to access issues, audibility and synchronization throughout the remainder of the project are acceptable.
|
FIR-Aging Inspection | 10/30/2006 | 10/30/2006 | 10/31/2006 | | DEFR |
Forrest France
|
|
|
|