INSP-Final Inspection | 10/20/2009 | 10/21/2009 | 10/21/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. The insulation issue is being addressed under the new permit FIR09-00609.
|
INSP-Final Inspection | 3/5/2008 | 3/6/2008 | 3/14/2008 | A | CANC |
Troy Cobbley
|
|
|
Will schedule when there is access to perform the life safety inspection.
|
INSP-Sprinkler Rough-in/Hydro | 3/13/2006 | 3/13/2006 | 3/13/2006 | A | PASS |
Troy Cobbley
|
|
|
Head spacing has been fixed but insulation is still hanging down and creating obstructions.
|
INSP-Sprinkler Rough-in/Hydro | 3/9/2006 | 3/10/2006 | 3/10/2006 | A | FAIL |
Troy Cobbley
|
|
|
Need to meet with the contractor to go over the new head spacing.
|
INSP-Sprinkler Rough-in/Hydro | 3/3/2006 | 3/6/2006 | 3/6/2006 | A | FAIL |
Troy Cobbley
|
|
|
Provide additional upright heads on the west side of the draft stop (approx. 10 heads) and add one upright head at verticle duct blockage in the southwest corner of project.
|
INSP-Sprinkler Rough-in/Hydro | 3/3/2006 | 3/3/2006 | 3/3/2006 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 3/3/2006 at 10:35:17 AM. Contact: ###-####.
|