Permit Information
Permit NumberFIR06-00073
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 6867 S SUPPLY WAY
Project NameSPR PERFORMANCE FRAMING
Customer Number 
ePlanReview 
Description
PERFORMANCE FRAMING - To install a wet, partial grid, Ordinary Hazard Group 2 fire sprinkler system in a new 11,700-ft/2, one story, pre-engineered metal building and related site improvements. The underground fire water service supply is included in this permit with connection located at the property line in "Supply Way." This building will be used for the fabrication of wood framed walls and building components for new residential homes. This building will be equipped with a dust collection system. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-01971.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/27/20073/2/20073/2/2007PPASS
DetailsForrest France
Final fire sprinkler inspection passed, flow switch delay adjusted while on site, permit finaled.
INSP-Sprinkler Rough-in/Hydro2/27/20073/2/20073/2/2007APART
DetailsForrest France
OH hydrostatic test passed. The OH rough-in installation is satisfactory, noted missing test orfice at remote inspectors test connection.
INSP-Sprinkler Rough-in/Hydro3/31/20064/4/20064/4/2006ACANC
DetailsForrest France
Scheduled by a contractor via Hello! on 3/31/2006 at 1:34:47 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Apr 4 2006 7:17AM.
INSP-Supply line flush3/31/20064/3/20064/3/2006APART
DetailsForrest France
UG fire supply line flush performed satisfactory.
INSP-Sprinkler Rough-in/Hydro3/28/20063/28/20063/28/2006APART
DetailsForrest France
UG supply line hydrostatic test inspection passed.
INSP-Supply line flush3/21/20063/23/20063/23/2006PPART
DetailsForrest France
UG fire supply line has been relocated to attain the proper depth of bury as required, thrust blocking verified, UG is okay to cover.
INSP-Supply line flush3/17/20063/20/20063/20/2006PFAIL
DetailsForrest France
Inspection was for UG supply line cover. Depth of bury for the entire pipe run does not meet the required 4'-6" to top of pipe for this locality (the actual install is approximately 3'-6" from top of pipe to floor slab at the building and 3'-6" to 4'-0" to grade for the remainder).