INSP-Final Inspection | 2/4/2008 | 2/4/2008 | 2/4/2008 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 1/29/2008 | 2/1/2008 | 2/1/2008 | P | FAIL |
Troy Cobbley
|
|
|
The first flow switch and pressure switch tested on the sprinkler system did not latch. Contractor was unable to reprogram at this tiem so the inspection was stopped. To be rescheduled for monday at 9:00am.
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2008 | 2/1/2008 | 1/29/2008 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Internet Inspection Request from: Robert Gobler Inspection cancelled from web by: Robert Gobler
|
INSP-Alarm Testing | 12/11/2007 | 12/12/2007 | 12/12/2007 | P | DONE |
Troy Cobbley
|
|
|
Inspected the kitchen area. See the approved plans for deficiencies.
|
INSP-Alarm Testing | 12/10/2007 | 12/11/2007 | 12/12/2007 | P | DONE |
Troy Cobbley
|
|
|
Area 6 has been finished up and area 8 almost finished. See the city approved plans for deficiencies in area 8.
|
INSP-Alarm Testing | 12/5/2007 | 12/6/2007 | 12/6/2007 | A | FAIL |
Troy Cobbley
|
|
|
Building #6 was inspected today. The devices operated correctly but the zone descriptions at the monitoring station were wrong. The inspection was stopped.
|
INSP-Final Inspection | 4/26/2006 | 4/27/2006 | 4/27/2006 | P | PART |
Troy Cobbley
|
|
|
The lobby area was inspected today and is approved except for one smoke detector in the administration area which needs to be relocated from a supply register. (The following was entered by Mike Timmerman) The remaining Out Buildings - Dining and Class Room have not been completed. This fire alarm work is required to be completed before this permit can be finaled.
|