Permit Information
Permit NumberFIR06-00091
StatusFinaled
Name SENTRY SECURITY SYSTEMS
Site Address 303 N ALLUMBAUGH ST
Project Namealm - INTERMOUNTAIN HOSPITAL
Customer Number 
ePlanReview 
Description
To upgrade the existing fire alarm components in the main lobby, classroom building and dining building. The FACP was installed under FIR03-00647, but will be relocated into the business office (other side of the wall) and a remote annunciator installed in the main corridor under this permit. The remainder of the building (north Annex) will be the final component of the upgrade, to be completed next year. The upgraded fire alarm system is a required manual fire alarm system with complete automatic detection, sprinkler monitoring, HVAC shutdown, door release, kitchen hood monitoring and fire/smoke damper release.

The associated building permit (BLD05-03003) is to upgrade the existing ceilings and door assemblies per Letter of Agreement (based on 2000 IBC) on file (copy attached to plans) to provide a fully complying 1-hour exit access corridor system in areas designated on plans as part of Phase IV. To upgrade all applicable life safety components (openings, penetrations, ducts, sprinklers & alarms) associated with the corridor upgrade as noted in plan review reports attached. (drs). (INTERMOUNTAIN HOSPITAL-PHASE IV UPGRADES-CORRIDOR)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/4/20082/4/20082/4/2008PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Alarm Testing1/29/20082/1/20082/1/2008PFAIL
DetailsTroy Cobbley
The first flow switch and pressure switch tested on the sprinkler system did not latch. Contractor was unable to reprogram at this tiem so the inspection was stopped. To be rescheduled for monday at 9:00am.
INSP-Sprinkler Rough-in/Hydro1/29/20082/1/20081/29/2008PCANC
DetailsTroy Cobbley
Phone #: ###-#### Internet Inspection Request from: Robert Gobler Inspection cancelled from web by: Robert Gobler
INSP-Alarm Testing12/11/200712/12/200712/12/2007PDONE
DetailsTroy Cobbley
Inspected the kitchen area. See the approved plans for deficiencies.
INSP-Alarm Testing12/10/200712/11/200712/12/2007PDONE
DetailsTroy Cobbley
Area 6 has been finished up and area 8 almost finished. See the city approved plans for deficiencies in area 8.
INSP-Alarm Testing12/5/200712/6/200712/6/2007AFAIL
DetailsTroy Cobbley
Building #6 was inspected today. The devices operated correctly but the zone descriptions at the monitoring station were wrong. The inspection was stopped.
INSP-Final Inspection4/26/20064/27/20064/27/2006PPART
DetailsTroy Cobbley
The lobby area was inspected today and is approved except for one smoke detector in the administration area which needs to be relocated from a supply register. (The following was entered by Mike Timmerman) The remaining Out Buildings - Dining and Class Room have not been completed. This fire alarm work is required to be completed before this permit can be finaled.