INSP-Final Inspection | 4/28/2006 | 5/1/2006 | 5/1/2006 | A | PASS |
Forrest France
|
|
|
Fire alarm corrections have been verified, permit work passed final inspection.
|
INSP-Final Inspection | 4/27/2006 | 4/28/2006 | 4/28/2006 | A | FAIL |
Forrest France
|
|
|
Tested notification and detection devices at the 10th and 11th floor machine rooms, helipad, elevator lobbies, mech. penthouse, tested manual pulls, smoke at nac panel, tested sprinkler tampers and flows at the 10th floor manifold. The notification devices at the north mech. penthouse 3rd floor failed to function properly, need to test sprinkler tampers and flows at the 4th floor and tamper at the 3rd floor at next inspection.
|
INSP-Final Inspection | 4/24/2006 | 4/26/2006 | 4/27/2006 | P | FAIL |
Forrest France
|
|
|
Waterflow alarms are addressed incorrectly, system has not been pre-tested prior to inspection, to be rescheduled.
|