INSP-Final Inspection | 11/7/2006 | 11/7/2006 | 11/7/2006 | P | PASS |
Forrest France
|
|
|
Inspected resubmittals, verified UG supply is approved for the 4" size installed, c/n items have been amended, noted to contractor to provide signage at the door to the riser room.
|
INSP-Final Inspection | 10/18/2006 | 10/19/2006 | 10/19/2006 | A | FAIL |
Troy Cobbley
|
|
|
See the front page of the city approved plans for the correction list which includes resubmitting the plans.
|
INSP-Final Inspection | 10/17/2006 | 10/18/2006 | 10/18/2006 | P | CANC |
Troy Cobbley
|
|
|
John said to cancel until the fire alarm is ready to be inspected.
|
INSP-Sprinkler Rough-in/Hydro | 10/12/2006 | 10/12/2006 | 10/12/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground and overhead hydro tests passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/2/2006 | 10/2/2006 | 10/2/2006 | P | FAIL |
Troy Cobbley
|
|
|
Overhead and underground hydro test failed
|
INSP-Supply line flush | 9/27/2006 | 9/27/2006 | 9/27/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in | 9/12/2006 | 9/13/2006 | 9/13/2006 | A | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover. Size of underground installed is 4". 6" is shown on the plans.
|
INSP-Sprinkler Rough-in | 9/5/2006 | 9/5/2006 | 9/6/2006 | P | FAIL |
Troy Cobbley
|
|
|
Underground piping is laying in the trench but thrust blocks and bury wire is missing. The piping does not meet the 4'-6" minimum bury depth. I went over this with the fire sprinkler and general conractor. They stated that the landscaping would be raised to meet code.
|
INSP-Supply line flush | 8/31/2006 | 9/1/2006 | 9/1/2006 | A | FAIL |
Forrest France
|
|
|
Partial underground, thrust blocks later Internet Inspection Request from: John Warnick NOTE: 4" pipe is installed and 6" fire service pipe is indicated on permit scope, tracer wire is not provided, the pipe installation does not meet min. depth of bury, approved plans not available on site for review, as noted by contractor thrust blocks are not completed at this time.
|
INSP-Sprinkler Rough-in | 4/18/2006 | 4/19/2006 | 4/19/2006 | P | PART |
Troy Cobbley
|
|
|
Inspection was for the piping above the units with hard lid ceilings. See city approved plans for locations where there is shadowing in the restrooms. The units with ceiling tile will be inspected when installed on site.
|