Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR06-00159
StatusFinaled
Name AUDIO ELECTRONICS INC
Site Address 417 S 6TH ST
Project Namealm ADA COUNTY JUSTICE CENTER
Customer Number 
ePlanReview 
Description
To provide a new fire alarm system in an existing building that includes sprinkler monitoring, elevator recall/shutdown, HVAC shutdown, fire/smoke damper control, security door release and notification throughout.

The associated with building permit (BLD 05-03414) is to remodel the 1st story (18,080 square feet) and the basement (25,500 square feet) of an existing 50,900 square foot building for a new office and storage tenant. Except for new exterior windows, a new exterior door, and a fire sprinkler system, an existing 7,320 square foot tenant space located on the 1st story is NOT within the scope of work allowed under this permit. Work is to include interior nonbearing walls, several restrooms accessible to the disabled, suspended ceilings, new exterior windows and doors, new single ply roof membrane and insulation, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Code. Site work including parking was done under permit BLD05-02914. Interior demolition was done under permit BLD05-03470. (DRH05-00230, CVA05-00019, and CUP05-00073) **CJW** (ADA COUNTY JUSTICE CENTER) This building is fire sprinklered for area increase.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/5/20067/5/20067/6/2006PPASS
DetailsForrest France
Correction notice items have been completed, final fire alarm inspection passed.
INSP-Final Inspection6/29/20066/30/20066/30/2006AFAIL
DetailsForrest France
One duct detector at first floor north plan FP2 failed to function, shunt trip for the elevator failed to operate, method to test the HD in the elevator control room not provided, need to remove cover at the sd above nac panel northeast side, security door is still not installed at the main entry exit.
INSP-Final Inspection6/26/20066/28/20066/28/2006AFAIL
DetailsForrest France
On site inspection approx. 2 hrs., inspected basement areas north and south and ground level area south. Correction items include PIV tamper, incorrect addressing at two in duct detectors, two restrooms with non-functional notification devices, changed EOL's, changed av location and type which will require as-built plans reflecting actual install as deviated from approved plans, security door at the main entry/exit is not installed at this time to enable testing of this point, provide list of signals recieved for verification at next inspection, per review comments NFPA record of inspection and testing to be completed by the contractor prior to request for final inspection.
INSP-Final Inspection6/15/20066/16/20066/15/2006ACANC
DetailsForrest France
Forrest, We would like to reschedule this for late AM if at all possible. Please let us know as soon as possible when you can make it. ###-####. Thanks, Jason; Phone #: ###-#### Internet Inspection Request from: Jason Minnick Inspection cancelled from web by: Jason Minnick
INSP-Final Inspection6/14/20066/15/20066/15/2006PCANC
DetailsForrest France
Forrest, We would like to schedule this walk thru for Ada County Justice Center. Please call us as soon as you know an approximate time. ###-####. Thanks, Jason; Phone #: ###-#### Internet Inspection Request from: Jason Minnick Inspection cancelled from web by: Jason Minnick