INSP-Final Inspection | 8/18/2006 | 8/21/2006 | 8/21/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/17/2006 | 8/18/2006 | 8/18/2006 | P | CANC |
Troy Cobbley
|
|
|
The fire alarm system was not ready to final yet
|
INSP-Sprinkler Rough-in/Hydro | 8/17/2006 | 8/17/2006 | 8/17/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/11/2006 | 8/14/2006 | 8/14/2006 | A | DONE |
Troy Cobbley
|
|
|
Began the 24 hour air test at 10:00am. The left system is at 41psi and the right system is at 40 psi.
|
INSP-Supply line flush | 7/27/2006 | 7/28/2006 | 7/28/2006 | A | PART |
Forrest France
|
|
|
UG fire supply line flush performed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 5/22/2006 | 5/22/2006 | 5/22/2006 | P | PART |
Forrest France
|
|
|
The remainder of UG fire supply line including the ductile riser stub is approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2006 | 5/22/2006 | 5/22/2006 | A | CANC |
Troy Cobbley
|
|
|
Contact: Jason - UG Cover Inspection; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in | 5/18/2006 | 5/18/2006 | 5/19/2006 | P | PART |
Troy Cobbley
|
|
|
Roughly half of the long run of 8" underground is ok to cover. The other half including the 90's has not been installed yet.
|
INSP-Sprinkler Rough-in | 5/15/2006 | 5/18/2006 | 5/18/2006 | A | CANC |
Troy Cobbley
|
|
|
rescheduled for afternoon
|