INSP-Final Inspection | 5/8/2006 | 5/8/2006 | 5/8/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 4/25/2006 | 4/25/2006 | 4/25/2006 | P | PART |
Forrest France
|
|
|
Overhead work is good for cover at the drop ceiling, final pending ceiling tile and escutcheon installation, will also need to verify riser is tagged with a current annual inspection for the existing system.
|
INSP-Sprinkler Rough-in/Hydro | 4/20/2006 | 4/21/2006 | 4/21/2006 | A | FAIL |
Troy Cobbley
|
|
|
The new sprinkler pendant has been added to an existing 1" drop, which means there are two heads being piped from a single 1" outlet. This new head needs to be fed from the 1 1/4" branchline piping as discussed or provide hydraulic calculations.
|