INSP-Final Inspection | 1/31/2007 | 2/1/2007 | 2/1/2007 | P | PASS |
Forrest France
|
|
|
Per field inspection completed by B. Johnson, the fire sprinkler installation is satisfactory. Noted several locations at tenant spaces where storage heights and housekeeping procedures are not code compliant.
|
INSP-Final Inspection | 1/30/2007 | 1/30/2007 | 1/30/2007 | P | NR |
Forrest France
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
INSP-Sprinkler Rough-in/Hydro | 11/13/2006 | 11/13/2006 | 11/13/2006 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test for overhead sprinkler piping from the Needle Works to the Cookie Lady has passed. This hydro test did not include the canopy.
|
INSP-Sprinkler Rough-in/Hydro | 7/27/2006 | 7/27/2006 | 7/27/2006 | P | PART |
Forrest France
|
|
|
OH hydrostatic test for phase 2 remodel including bld 2 and 3 is satisfactory, OH rough in is good for cover at the drop ceiling areas for bld 2 and 3- fire caulking at 2-hr wall penetrations completed while on site.
|
INSP-Sprinkler Rough-in/Hydro | 7/25/2006 | 7/26/2006 | 7/27/2006 | P | DEFR |
Forrest France
|
|
|
Inspection rescheduled per phone call from contractor.
|