Permit Information
Permit NumberFIR06-00449
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 800 S VISTA AVE
Project NameSPR VISTA VILLAGE-PHASE II
Customer Number 
ePlanReview 
Description
VISTA VILLAGE SHOPPING CENTER (BLD "B" CANOPY, BLD A-1 & A-2) * To add fire sprinklers from an added antifreeze system, connected to the existing system for a new front facade/canopy being constructed on an existing, single story, CMU exterior wall, Type V-B, retail building. This building is fire sprinklered for area increase. The fire sprinkler system work shall comply with the IFC 2000, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-02464.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/20/20083/20/20083/20/2008PPASS
DetailsForrest France
Fire sprinkler permit finaled.
FIR-Aging Inspection3/20/20083/20/20083/20/2008PDONE
DetailsForrest France
Permit work completed, doc final pending.
INSP-Final Inspection2/23/20072/26/20072/26/2007PFAIL
DetailsForrest France
Missing escutcheons at exterior canopy pendents.
INSP-Final Inspection2/23/20072/26/20072/23/2007ACANC
DetailsForrest France
Scheduled by a contractor via Hello! on 2/23/2007 at 1:02:01 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Feb 23 2007 1:11PM.
INSP-Final Inspection1/31/20072/1/20072/1/2007PFAIL
DetailsForrest France
Per field inspection by B. Johnson, items needed for final include missing ceiling tiles, hard lids at canopy, fireproofing at the riser room.
INSP-Final Inspection1/30/20071/30/20071/30/2007PFAIL
DetailsForrest France
Provide forward flow test, certify RP backflow device, ball drip on the FDC is not installed correctly, missing head wrench.
INSP-Sprinkler Rough-in1/19/20071/22/20071/22/2007APART
DetailsForrest France
OH rough-in for building A-1 wet and antifreeze systems is satisfactory. Contractor also completed UG supply line hydrostatic test acceptable.
INSP-Final Inspection1/19/20071/19/20071/19/2007PNR
DetailsForrest France
Project is not ready for final inspection at this time.
INSP-Sprinkler Rough-in/Hydro1/19/20071/19/20071/19/2007PPART
DetailsForrest France
Overhead hydrostatic testing of the new wet and antifreeze system completed satisfactory.
INSP-Sprinkler Rough-in/Hydro11/13/200611/13/200611/13/2006PCANC
DetailsTroy Cobbley
Hydro test was for the retail store areas and not the canopy
INSP-Sprinkler Rough-in/Hydro9/28/20069/29/20069/29/2006PPART
DetailsForrest France
OH hydro and rough-in inspection for the antifreeze system at the front canopy as marked on plans are acceptable pending two heads at the north overbuild which need to be raised and three heads at the front canopy are partially blocked by an adjacent soffit.
INSP-Sprinkler Rough-in/Hydro8/28/20068/28/20068/28/2006PPART
DetailsForrest France
Hydrostatic test for a portion of the antifreeze system at the front canopy as marked on approved plans is okay.
INSP-Sprinkler Rough-in/Hydro8/25/20068/25/20068/28/2006PPART
DetailsForrest France
OH rough-in for a portion of the canopy antifreeze system is good for cover as marked on approved plans, flexible couplings where pipe passes through brick walls at two locations to be installed and verified at next inspection, plywood obstruction in the truss web to be removed per general contractor.