INSP-Final Inspection | 8/29/2006 | 8/29/2006 | 8/29/2006 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 8/21/2006 | 8/21/2006 | 8/21/2006 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2006 | 8/21/2006 | 8/21/2006 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/17/2006 | 8/18/2006 | 8/18/2006 | A | PASS |
Troy Cobbley
|
|
|
Canopy hydro test passed. The 24 hour air test was started at 1:30 with 45psi of air showing on the guage. A check vavle is missing in the air line and will need to be added.
|
INSP-Sprinkler Rough-in/Hydro | 8/16/2006 | 8/17/2006 | 8/18/2006 | A | CANC |
Troy Cobbley
|
|
|
Contractor is not ready for inspection.
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2006 | 8/17/2006 | 8/17/2006 | | DONE |
Troy Cobbley
|
|
|
###-#### - johnthan
|
INSP-Sprinkler Rough-in | 7/20/2006 | 7/21/2006 | 7/21/2006 | A | PASS |
Troy Cobbley
|
|
|
See marked plans for more areas that the sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 7/19/2006 | 7/20/2006 | 7/20/2006 | A | PASS |
Troy Cobbley
|
|
|
See marked plans for additional areas that are ok to cover and areas that require corrections.
|
INSP-Sprinkler Rough-in | 7/19/2006 | 7/21/2006 | 7/19/2006 | A | CANC |
Troy Cobbley
|
|
|
Mike is the contact @ ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Trent Bice Inspection cancelled from web by: Trent Bice
|
INSP-Sprinkler Rough-in | 7/11/2006 | 7/12/2006 | 7/12/2006 | A | FAIL |
Troy Cobbley
|
|
|
The work that needed inspected does not have an issued plan yet. It requires resubmittals.
|
INSP-Conference | 7/5/2006 | 7/6/2006 | 7/6/2006 | A | DONE |
Troy Cobbley
|
|
|
I went over the sprinkler requirements for the inside of the mountain that is to be installed.
|