Permit Information
Permit NumberFIR06-00463
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 6590 W NORWOOD DR
Project NameDR ROMAN SCHWARTSMAN
Customer Number 
ePlanReview 
Description
DR. ROMAN SCHWARTSMAN MEDICAL OFFICE BUILDING - To install a complete overhead wet and dry system in a new 9,900-ft/2, two story, metal frame and masonry orthopedic medical office building. This building will be fully fire sprinklered throughout the first floor parking garage, lobby, exit stairs and electrical room and the medical office on the second floor. This building is designed as non-separated uses. The First Floor: 5,000-ft/2 and the Second Floor: 4,900-ft/2. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. The underground fire service supply was installed under separate permit FIR06-00303, of which both are attached to building permit: BLD06-00008.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/15/200611/17/200611/17/2006APASS
DetailsTroy Cobbley
Permit finaled. Forward flush passed.
INSP-Final Inspection11/3/200611/3/200611/3/2006PCANC
DetailsForrest France
call scott carter before going out ###-#### Internet Inspection Request from: Darla Downs
INSP-Sprinkler Rough-in/Hydro10/26/200610/27/200610/27/2006PPASS
DetailsTroy Cobbley
Overhead wet and dry systems including the fdc have passed the hydro tests.
INSP-Sprinkler Rough-in/Hydro10/24/200610/24/200610/24/2006PPART
DetailsForrest France
Begin 24 hour air test of the dry system at 1:45 @ 41.5 psi.
INSP-Sprinkler Rough-in/Hydro10/23/200610/23/200610/23/2006PFAIL
DetailsForrest France
AG hydrostatic test of the wet system failed due to approx. 9psi pressure loss and a leak at one location. The dry system gauge read below 200psi at the conclusion of the test. Also noted 24hr air test needs to be completed for the dry system.
INSP-Sprinkler Rough-in/Hydro10/19/200610/20/200610/20/2006PFAIL
DetailsTroy Cobbley
Hydro test failed
INSP-Sprinkler Rough-in/Hydro10/6/200610/9/200610/9/2006APASS
DetailsTroy Cobbley
2nd floor sprinkler piping is ok to cover
INSP-Sprinkler Rough-in8/14/20068/15/20068/15/2006PPASS
DetailsTroy Cobbley
Sprinkler rough-in passed. Additional coverage is required under the intermediate landing in both stairwells. Riser items not completed yet.