INSP-Final Inspection | 11/15/2006 | 11/17/2006 | 11/17/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush passed.
|
INSP-Final Inspection | 11/3/2006 | 11/3/2006 | 11/3/2006 | P | CANC |
Forrest France
|
|
|
call scott carter before going out ###-#### Internet Inspection Request from: Darla Downs
|
INSP-Sprinkler Rough-in/Hydro | 10/26/2006 | 10/27/2006 | 10/27/2006 | P | PASS |
Troy Cobbley
|
|
|
Overhead wet and dry systems including the fdc have passed the hydro tests.
|
INSP-Sprinkler Rough-in/Hydro | 10/24/2006 | 10/24/2006 | 10/24/2006 | P | PART |
Forrest France
|
|
|
Begin 24 hour air test of the dry system at 1:45 @ 41.5 psi.
|
INSP-Sprinkler Rough-in/Hydro | 10/23/2006 | 10/23/2006 | 10/23/2006 | P | FAIL |
Forrest France
|
|
|
AG hydrostatic test of the wet system failed due to approx. 9psi pressure loss and a leak at one location. The dry system gauge read below 200psi at the conclusion of the test. Also noted 24hr air test needs to be completed for the dry system.
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2006 | 10/20/2006 | 10/20/2006 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test failed
|
INSP-Sprinkler Rough-in/Hydro | 10/6/2006 | 10/9/2006 | 10/9/2006 | A | PASS |
Troy Cobbley
|
|
|
2nd floor sprinkler piping is ok to cover
|
INSP-Sprinkler Rough-in | 8/14/2006 | 8/15/2006 | 8/15/2006 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in passed. Additional coverage is required under the intermediate landing in both stairwells. Riser items not completed yet.
|