INSP-Final Inspection | 8/3/2006 | 8/3/2006 | 8/3/2006 | P | PASS |
Forrest France
|
|
|
Items on previous c/n have been verified for completion, fire sprinkler permit finaled.
|
INSP-Final Inspection | 7/30/2006 | 7/31/2006 | 7/31/2006 | A | FAIL |
Forrest France
|
|
|
One pendent head above office next to ductwork is damaged and needs to be replaced, remove plastic shipping guards from heads in 4 locations, provide missing 2nd pc canopy at 401 in restroom.
|
INSP-Final Inspection | 7/27/2006 | 7/28/2006 | 7/30/2006 | P | DEFR |
Forrest France
|
|
|
No time available for this inspection today, to be rescheduled.
|
INSP-Sprinkler Rough-in | 7/13/2006 | 7/13/2006 | 7/13/2006 | P | PASS |
Troy Cobbley
|
|
|
Rough-in inspection passed.
|
INSP-Sprinkler Rough-in | 7/11/2006 | 7/12/2006 | 7/12/2006 | A | FAIL |
Troy Cobbley
|
|
|
Head spacing and supply piping at the full height wall needs to be addressed. Total of three heads. Problems have been discussed with Mick.
|