INSP-Final Inspection | 3/7/2007 | 3/8/2007 | 3/8/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | CANC |
Troy Cobbley
|
|
|
FIre alarm was not ready so this inspection could not be completed.
|
INSP-Final Inspection | 2/28/2007 | 3/1/2007 | 3/1/2007 | P | CANC |
Troy Cobbley
|
|
|
CONTACT: TODD Phone #: ###-#### Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 2/12/2007 | 2/13/2007 | 2/13/2007 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2006 | 12/13/2006 | 12/13/2006 | P | PART |
Troy Cobbley
|
|
|
Dry system hydro test passed. The FDC hydro test failed.
|
INSP-Supply line flush | 11/13/2006 | 11/13/2006 | 11/13/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 10/23/2006 | 10/24/2006 | 10/24/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 10/23/2006 | 10/24/2006 | 10/24/2006 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Sprinkler Rough-in | 9/13/2006 | 9/14/2006 | 9/14/2006 | A | DONE |
Troy Cobbley
|
|
|
Duplicate inspection. Underground supply piping is ok to cover
|
INSP-Sprinkler Rough-in | 9/12/2006 | 9/12/2006 | 9/12/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground piping is ok to cover
|